Tender SURE Phase A, Package 7 — RRM Road, Lavelle Road, Brigade Road (Bengaluru Smart City)

Smart City (Tender SURE) redevelopment of three central roads, reported as completed in the Feb 2021 status presentation.

Location
Central Bengaluru (Lavelle Road, Brigade Road, Raja Ram Mohan Roy Road)
Alignment drawn
3.4 km · approximate (OpenStreetMap)
Documents
2
Verified facts
8 of 8
8 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

Phase A Package 7

Bengaluru Smart City's Tender SURE Phase A, Package 7.

VerifiedOfficial record

Contractor

M/s B K Vinod Kumar

The presentation lists the Package 7 agency as “M/s B K Vinod Kumar”.

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Contract value

₹35.41 crore

The project status table gives an awarded amount of ₹35.41 crore against a DPR cost of ₹39.97 crore; the package summary gives a project cost of 35.41 Cr.

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Work order date

01.03.2019

The work order is dated 01.03.2019; the site was handed over on 25.04.2019.

VerifiedOfficial record

Period of completion

15 Months

The package duration is given as 15 months.

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Roads covered

Raja Ram Mohan Roy Road, Lavelle Road, Brigade Road

Package 7 covers Raja Ram Mohan Roy Road (Richmond Circle to Hudson Circle, 1.00 km), Lavelle Road (M.G. Road to Richmond Circle, 1.38 km) and Brigade Road (M.G. Road to War Memorial Junction, 0.32 km).

Package 7 1. Raja Ram Mohan Roy Road from Richmond Circle to Hudson Circle. 1.00 19 2. Lavelle Road from M.G.Road to Richmond Circle. 1.38 20 3. Brigade Road from M.G.Road to War Memorial Junction. 0.32

[2]Tender SURE Phase A roads — project status presentation (Feb 2021), p. 2

VerifiedOfficial record

Stage of work

Completed

As of the presentation (dated 9 Feb 2021), the status of work is “Completed”, with financial progress of 99% (₹34.89 crore).

VerifiedOfficial record

Audit finding

Foot bridge construction without informing BenSCL violated Tender SURE guidelines

CAG Report No. 11 of 2025 notes that the Tender SURE guidelines aimed to stop repeated civil works by utility agencies, and records that BBMP's construction of a foot bridge on a Bengaluru smart road without informing BenSCL violated those guidelines. The finding is not specific to Package 7.

The Tender SURE Guidelines aimed at solving issues of non-usability of road network due to frequent civil works undertaken by multiple utility agencies

[11]CAG Report No. 11 of 2025 — Implementation of Smart City Mission, Government of Karnataka, p. 28

VerifiedOfficial record