Skip to content
CivicProof

Project record

MRL6-Seegepalya to Hulikunte Via, Apakaranahalli

PMGSY-II · package KN02113 · Doddaballapur block · Maintenance

Location
Doddaballapur block, Bengaluru Rural district
Alignment drawn
none published: found by name
Documents
3
Verified facts
11 of 11
11 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

MRL6-Seegepalya to Hulikunte Via, Apakaranahalli

OMMAS lists PMGSY-II work KN02113 as “MRL6-Seegepalya to Hulikunte Via, Apakaranahalli”.

Road Name / Bridge Name: MRL6-Seegepalya to Hulikunte Via, Apakaranahalli

[1]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-II (CSV export), p. 1

VerifiedOfficial record

Project / work ID

KN02113

OMMAS package number KN02113.

VerifiedOfficial record

Responsible agency

DPIU Of Bangalore r

The programme implementation unit is recorded as “DPIU Of Bangalore r”.

Programme Implementation Unit: DPIU Of Bangalore r

[3]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-II (CSV export), p. 1

VerifiedOfficial record

Contractor

VINYAS BUILDERS

OMMAS lists the contractor for this work as “VINYAS BUILDERS”.

Contractor Name: VINYAS BUILDERS [01 Mar 2014]

[4]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-II (CSV export), p. 1

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹126.86 lakh

The sanction cost is recorded as 126.86 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹12.40 lakh

The “5 Years Maintenance Cost Due” column shows 12.40 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

15-12-2015

The completion date column reads “Financial: 15-03-2017/ Physical: 15-12-2015”; the physical completion date is 15-12-2015.

Completion Date: Financial: 15-03-2017/ Physical: 15-12-2015

[10]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-II (CSV export), p. 1

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

4.240 km

Road length 4.240 km; 4.240 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record

Quality inspection

Satisfactory

Quality monitoring, Jan 2016 to Sep 2026: 1 National and 8 State Quality Monitor inspection(s); grade recorded “Satisfactory”.

NQM* Inspection Count: 1; NQM* Grade: Satisfactory; SQM# Inspection Count: 8; SQM# Grade: Satisfactory

[13]Works Wise Grading Abstract — NQM/SQM inspections, Bangalore R, Jan 2016 to Sep 2026 (CSV export), p. 3

VerifiedOfficial record