Project record
MRL3-Ajjagondanahally to Muthsandra MDR Via., Gulakaipura
PMGSY-II · package KN02115 · Hosakote block · Maintenance
- Location
- Hosakote block, Bengaluru Rural district
- Alignment drawn
- none published: found by name
- Documents
- 3
- Verified facts
- 11 of 11
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
MRL3-Ajjagondanahally to Muthsandra MDR Via., Gulakaipura
OMMAS lists PMGSY-II work KN02115 as “MRL3-Ajjagondanahally to Muthsandra MDR Via., Gulakaipura”.
Road Name / Bridge Name: MRL3-Ajjagondanahally to Muthsandra MDR Via., Gulakaipura
[1]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-II (CSV export), p. 2
Project / work ID
KN02115
OMMAS package number KN02115.
Package No.: KN02115
[2]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-II (CSV export), p. 2
Responsible agency
DPIU Of Bangalore r
The programme implementation unit is recorded as “DPIU Of Bangalore r”.
Programme Implementation Unit: DPIU Of Bangalore r
[3]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-II (CSV export), p. 2
Contractor
M N CHANDRASHEKARAIAH
OMMAS lists the contractor for this work as “M N CHANDRASHEKARAIAH”.
Contractor Name: M N CHANDRASHEKARAIAH [28 Feb 2014]
[4]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-II (CSV export), p. 2
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹234.46 lakh
The sanction cost is recorded as 234.46 (₹ lakh).
Sanction Cost: 234.46
[5]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-II (CSV export), p. 2
Maintenance cost due
₹17.48 lakh
The “5 Years Maintenance Cost Due” column shows 17.48 (₹ lakh).
5 Years Maintenance Cost Due: 17.48
[9]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-II (CSV export), p. 2
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-03-2015
The completion date column reads “Financial: 06-02-2017/ Physical: 31-03-2015”; the physical completion date is 31-03-2015.
Completion Date: Financial: 06-02-2017/ Physical: 31-03-2015
[10]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-II (CSV export), p. 2
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
5.980 km
Road length 5.980 km; 5.980 km recorded as completed.
Road Length (Kms): 5.980
[7]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-II (CSV export), p. 2
Stage of work
Maintenance
OMMAS records the stage of progress as “Maintenance”.
Stage of Progress: Maintenance
[8]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-II (CSV export), p. 2
Quality inspection
Satisfactory
Quality monitoring, Jan 2016 to Sep 2026: 1 National and 4 State Quality Monitor inspection(s); grade recorded “Satisfactory”.
NQM* Inspection Count: 1; NQM* Grade: Satisfactory; SQM# Inspection Count: 4; SQM# Grade: Satisfactory
[13]Works Wise Grading Abstract — NQM/SQM inspections, Bangalore R, Jan 2016 to Sep 2026 (CSV export), p. 4