Project record

MRL24-Banamakanahally MDR to Gundrahally via Agasarahally, Marasandrahally, Sathiganahally, Hedakanahally

PMGSY-III · package KN02126 · Hosakote block · Maintenance

Location
Hosakote block, Bengaluru Rural district
Alignment drawn
4.6 km · official GIS
Documents
3
Verified facts
11 of 11
11 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

OMMAS lists PMGSY-III work KN02126 as “MRL24-Banamakanahally MDR to Gundrahally via Agasarahally, Marasandrahally, Sathiganahally, Hedakanahally”.

Road Name / Bridge Name: MRL24-Banamakanahally MDR to Gundrahally via Agasarahally, Marasandrahally, Sathiganahally, Hedakanahally

[1]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 2

VerifiedOfficial record

Project / work ID

KN02126

OMMAS package number KN02126.

VerifiedOfficial record

Responsible agency

DPIU Of Bangalore r

The programme implementation unit is recorded as “DPIU Of Bangalore r”.

Programme Implementation Unit: DPIU Of Bangalore r

[3]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 2

VerifiedOfficial record

Contractor

MGANESH

OMMAS lists the contractor for this work as “MGANESH”.

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹329.97 lakh

The sanction cost is recorded as 329.97 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹22.02 lakh

The “5 Years Maintenance Cost Due” column shows 22.02 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

01-06-2021

The completion date column reads “Financial: 30-10-2021/ Physical: 01-06-2021”; the physical completion date is 01-06-2021.

Completion Date: Financial: 30-10-2021/ Physical: 01-06-2021

[10]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 2

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

5.960 km

Road length 5.960 km; 5.732 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record

Quality inspection

Satisfactory

Quality monitoring, Jan 2016 to Sep 2026: 0 National and 8 State Quality Monitor inspection(s); grade recorded “Satisfactory”.

NQM* Inspection Count: 0; NQM* Grade: --; SQM# Inspection Count: 8; SQM# Grade: Satisfactory

[13]Works Wise Grading Abstract — NQM/SQM inspections, Bangalore R, Jan 2016 to Sep 2026 (CSV export), p. 4

VerifiedOfficial record