Project record
MRL05-Doddakoliga MDR TO Doddanallurahally MDR VIA, Chikkanallurahally, Beguru , Beemakanahally, Bagalur
PMGSY-III · package KN02129 · Hosakote block · Maintenance
- Location
- Hosakote block, Bengaluru Rural district
- Alignment drawn
- 22 m · official GIS
- Documents
- 3
- Verified facts
- 11 of 11
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
OMMAS lists PMGSY-III work KN02129 as “MRL05-Doddakoliga MDR TO Doddanallurahally MDR VIA, Chikkanallurahally, Beguru , Beemakanahally, Bagalur”.
Road Name / Bridge Name: MRL05-Doddakoliga MDR TO Doddanallurahally MDR VIA, Chikkanallurahally, Beguru , Beemakanahally, Bagalur
[1]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 2
Project / work ID
KN02129
OMMAS package number KN02129.
Package No.: KN02129
[2]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 2
Responsible agency
DPIU Of Bangalore r
The programme implementation unit is recorded as “DPIU Of Bangalore r”.
Programme Implementation Unit: DPIU Of Bangalore r
[3]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 2
Contractor
B.N. Devaraj
OMMAS lists the contractor for this work as “B.N. Devaraj”.
Contractor Name: B.N. Devaraj [15 Jun 2020]
[4]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 2
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹373.24 lakh
The sanction cost is recorded as 373.24 (₹ lakh).
Sanction Cost: 373.24
[5]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 2
Maintenance cost due
₹34.20 lakh
The “5 Years Maintenance Cost Due” column shows 34.20 (₹ lakh).
5 Years Maintenance Cost Due: 34.20
[9]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 2
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
01-06-2021
The completion date column reads “Financial: 17-08-2021/ Physical: 01-06-2021”; the physical completion date is 01-06-2021.
Completion Date: Financial: 17-08-2021/ Physical: 01-06-2021
[10]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 2
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
6.160 km
Road length 6.160 km; 6.126 km recorded as completed.
Road Length (Kms): 6.160
[7]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 2
Stage of work
Maintenance
OMMAS records the stage of progress as “Maintenance”.
Stage of Progress: Maintenance
[8]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 2
Quality inspection
Satisfactory
Quality monitoring, Jan 2016 to Sep 2026: 1 National and 11 State Quality Monitor inspection(s); grade recorded “Satisfactory”.
NQM* Inspection Count: 1; NQM* Grade: Satisfactory; SQM# Inspection Count: 11; SQM# Grade: Satisfactory
[13]Works Wise Grading Abstract — NQM/SQM inspections, Bangalore R, Jan 2016 to Sep 2026 (CSV export), p. 4