Project record
MRL15-Hanumanthegowdanapalya MDR to Taluk Border via Srinivasapura, Srinivasapura Colony, Hanchipura, Kakkepalya, Kodappanahalli
PMGSY-III · package KN02134 · Nelamangala block · Maintenance
- Location
- Nelamangala block, Bengaluru Rural district
- Alignment drawn
- 2.6 km · official GIS
- Documents
- 3
- Verified facts
- 11 of 11
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
OMMAS lists PMGSY-III work KN02134 as “MRL15-Hanumanthegowdanapalya MDR to Taluk Border via Srinivasapura, Srinivasapura Colony, Hanchipura, Kakkepalya, Kodappanahalli”.
Road Name / Bridge Name: MRL15-Hanumanthegowdanapalya MDR to Taluk Border via Srinivasapura, Srinivasapura Colony, Hanchipura, Kakkepalya, Kodappanahalli
[1]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 3
Project / work ID
KN02134
OMMAS package number KN02134.
Package No.: KN02134
[2]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 3
Responsible agency
DPIU Of Bangalore r
The programme implementation unit is recorded as “DPIU Of Bangalore r”.
Programme Implementation Unit: DPIU Of Bangalore r
[3]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 3
Contractor
Sri Chowdeshwari
OMMAS lists the contractor for this work as “Sri Chowdeshwari”.
Contractor Name: Sri Chowdeshwari [15 Jun 2020]
[4]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 3
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹310.24 lakh
The sanction cost is recorded as 310.24 (₹ lakh).
Sanction Cost: 310.24
[5]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 3
Maintenance cost due
₹34.44 lakh
The “5 Years Maintenance Cost Due” column shows 34.44 (₹ lakh).
5 Years Maintenance Cost Due: 34.44
[9]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 3
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
01-06-2021
The completion date column reads “Financial: 01-10-2021/ Physical: 01-06-2021”; the physical completion date is 01-06-2021.
Completion Date: Financial: 01-10-2021/ Physical: 01-06-2021
[10]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 3
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
6.490 km
Road length 6.490 km; 6.490 km recorded as completed.
Road Length (Kms): 6.490
[7]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 3
Stage of work
Maintenance
OMMAS records the stage of progress as “Maintenance”.
Stage of Progress: Maintenance
[8]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 3
Quality inspection
Satisfactory
Quality monitoring, Jan 2016 to Sep 2026: 0 National and 8 State Quality Monitor inspection(s); grade recorded “Satisfactory”.
NQM* Inspection Count: 0; NQM* Grade: --; SQM# Inspection Count: 8; SQM# Grade: Satisfactory
[13]Works Wise Grading Abstract — NQM/SQM inspections, Bangalore R, Jan 2016 to Sep 2026 (CSV export), p. 5