MRL17-NH-207 to Yelahanka Vijayapura Road(MDR-4) via, Haralur, Polanahally, Mattabaralu

PMGSY-III · package KN02135 · Devanahalli block · Maintenance

Location
Devanahalli block, Bengaluru Rural district
Alignment drawn
6.7 km · official GIS
Documents
3
Verified facts
11 of 11
11 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

MRL17-NH-207 to Yelahanka Vijayapura Road(MDR-4) via, Haralur, Polanahally, Mattabaralu

OMMAS lists PMGSY-III work KN02135 as “MRL17-NH-207 to Yelahanka Vijayapura Road(MDR-4) via, Haralur, Polanahally, Mattabaralu”.

Road Name / Bridge Name: MRL17-NH-207 to Yelahanka Vijayapura Road(MDR-4) via, Haralur, Polanahally, Mattabaralu

[1]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Project / work ID

KN02135

OMMAS package number KN02135.

VerifiedOfficial record

Responsible agency

DPIU Of Bangalore r

The programme implementation unit is recorded as “DPIU Of Bangalore r”.

Programme Implementation Unit: DPIU Of Bangalore r

[3]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Contractor

B.N. Devaraj

OMMAS lists the contractor for this work as “B.N. Devaraj”.

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹434.66 lakh

The sanction cost is recorded as 434.66 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹43.03 lakh

The “5 Years Maintenance Cost Due” column shows 43.03 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

10-03-2022

The completion date column reads “Financial: 03-08-2022/ Physical: 10-03-2022”; the physical completion date is 10-03-2022.

Completion Date: Financial: 03-08-2022/ Physical: 10-03-2022

[10]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

7.310 km

Road length 7.310 km; 7.310 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record

Quality inspection

Satisfactory

Quality monitoring, Jan 2016 to Sep 2026: 0 National and 9 State Quality Monitor inspection(s); grade recorded “Satisfactory”.

NQM* Inspection Count: 0; NQM* Grade: --; SQM# Inspection Count: 9; SQM# Grade: Satisfactory

[13]Works Wise Grading Abstract — NQM/SQM inspections, Bangalore R, Jan 2016 to Sep 2026 (CSV export), p. 2

VerifiedOfficial record