N H 7 - Kundhana

PMGSY-I · package KN0220 · Devanahalli block · Completed

Location
Devanahalli block, Bengaluru Rural district
Alignment drawn
none published: found by name
Documents
3
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

N H 7 - Kundhana

OMMAS lists PMGSY-I work KN0220 as “N H 7 - Kundhana”.

VerifiedOfficial record

Project / work ID

KN0220

OMMAS package number KN0220.

VerifiedOfficial record

Responsible agency

DPIU Of Bangalore r

The programme implementation unit is recorded as “DPIU Of Bangalore r”.

Programme Implementation Unit: DPIU Of Bangalore r

[3]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-I (CSV export), p. 3

VerifiedOfficial record

Contractor

M/s. Ganesh Enterprises Sri K B Ramesh

OMMAS lists the contractor for this work as “M/s. Ganesh Enterprises Sri K B Ramesh”.

Contractor Name: M/s. Ganesh Enterprises Sri K B Ramesh [23 Jan 2007]

[4]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-I (CSV export), p. 3

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹158.50 lakh

The sanction cost is recorded as 158.50 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹13.17 lakh

The “5 Years Maintenance Cost Due” column shows 13.17 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

31-05-2008

The completion date column reads “Financial: 16-09-2008/ Physical: 31-05-2008”; the physical completion date is 31-05-2008.

Completion Date: Financial: 16-09-2008/ Physical: 31-05-2008

[10]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-I (CSV export), p. 3

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

10.600 km

Road length 10.600 km; 10.600 km recorded as completed.

VerifiedOfficial record

Stage of work

Completed

OMMAS records the stage of progress as “Completed”.

VerifiedOfficial record