Project record
T.Hosahalli - T15
PMGSY-I · package KN0295 · Doddaballapur block · Completed
- Location
- Doddaballapur block, Bengaluru Rural district
- Alignment drawn
- none published: found by name
- Documents
- 3
- Verified facts
- 11 of 11
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
T.Hosahalli - T15
OMMAS lists PMGSY-I work KN0295 as “T.Hosahalli - T15”.
Road Name / Bridge Name: T.Hosahalli - T15
[1]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-I (CSV export), p. 10
Project / work ID
KN0295
OMMAS package number KN0295.
Package No.: KN0295
[2]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-I (CSV export), p. 10
Responsible agency
DPIU Of Bangalore r
The programme implementation unit is recorded as “DPIU Of Bangalore r”.
Programme Implementation Unit: DPIU Of Bangalore r
[3]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-I (CSV export), p. 10
Contractor
M/s. Ganesh Enterprises Sri K B Ramesh
OMMAS lists the contractor for this work as “M/s. Ganesh Enterprises Sri K B Ramesh”.
Contractor Name: M/s. Ganesh Enterprises Sri K B Ramesh [14 Aug 2009]
[4]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-I (CSV export), p. 10
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹152.35 lakh
The sanction cost is recorded as 152.35 (₹ lakh).
Sanction Cost: 152.35
[5]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-I (CSV export), p. 10
Maintenance cost due
₹13.17 lakh
The “5 Years Maintenance Cost Due” column shows 13.17 (₹ lakh).
5 Years Maintenance Cost Due: 13.17
[9]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-I (CSV export), p. 10
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-05-2011
The completion date column reads “Financial: 25-11-2011/ Physical: 31-05-2011”; the physical completion date is 31-05-2011.
Completion Date: Financial: 25-11-2011/ Physical: 31-05-2011
[10]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-I (CSV export), p. 10
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
6.240 km
Road length 6.240 km; 6.240 km recorded as completed.
Road Length (Kms): 6.240
[7]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-I (CSV export), p. 10
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Bangalore R, PMGSY-I (CSV export), p. 10
Quality inspection
Satisfactory
Quality monitoring, Jan 2016 to Sep 2026: 0 National and 1 State Quality Monitor inspection(s); grade recorded “Satisfactory”.
NQM* Inspection Count: 0; NQM* Grade: --; SQM# Inspection Count: 1; SQM# Grade: Satisfactory
[13]Works Wise Grading Abstract — NQM/SQM inspections, Bangalore R, Jan 2016 to Sep 2026 (CSV export), p. 2