Project record

B.B.road to Somenahalli

PMGSY-I · package KN1902 · Gudibanda block · Maintenance

Location
Gudibanda block, Chikkaballapura district
Alignment drawn
none published: found by name
Documents
2
Verified facts
9 of 9
9 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

B.B.road to Somenahalli

OMMAS lists PMGSY-I work KN1902 as “B.B.road to Somenahalli”.

Road Name / Bridge Name: B.B.road to Somenahalli

[1]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 15

VerifiedOfficial record

Project / work ID

KN1902

OMMAS package number KN1902.

VerifiedOfficial record

Responsible agency

DPIU Of Chikkaballapur

The programme implementation unit is recorded as “DPIU Of Chikkaballapur”.

Programme Implementation Unit: DPIU Of Chikkaballapur

[3]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 15

VerifiedOfficial record

Contractor

B.Bhaskar Naidu

OMMAS lists the contractor for this work as “B.Bhaskar Naidu”.

Contractor Name: B.Bhaskar Naidu [18 Aug 2001]

[4]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 15

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹34.42 lakh

The sanction cost is recorded as 34.42 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

30-09-2003

The completion date column reads “Financial: 01-04-2005/ Physical: 30-09-2003”; the physical completion date is 30-09-2003.

Completion Date: Financial: 01-04-2005/ Physical: 30-09-2003

[9]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 15

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[10]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

5.150 km

Road length 5.150 km; 5.150 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record