Project record
gummaulapalli - T-03
PMGSY-I · package KN19109 · Bagepalli block · Completed
- Location
- Bagepalli block, Chikkaballapura district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
gummaulapalli - T-03
OMMAS lists PMGSY-I work KN19109 as “gummaulapalli - T-03”.
Road Name / Bridge Name: gummaulapalli - T-03
[1]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 3
Project / work ID
KN19109
OMMAS package number KN19109.
Package No.: KN19109
[2]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 3
Responsible agency
DPIU Of Chikkaballapur
The programme implementation unit is recorded as “DPIU Of Chikkaballapur”.
Programme Implementation Unit: DPIU Of Chikkaballapur
[3]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 3
Contractor
Byrappa
OMMAS lists the contractor for this work as “Byrappa”.
Contractor Name: Byrappa [23 Sep 2009]
[4]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 3
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹137.21 lakh
The sanction cost is recorded as 137.21 (₹ lakh).
Sanction Cost: 137.21
[5]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 3
Maintenance cost due
₹10.07 lakh
The “5 Years Maintenance Cost Due” column shows 10.07 (₹ lakh).
5 Years Maintenance Cost Due: 10.07
[9]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 3
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-03-2011
The completion date column reads “Financial: 05-07-2011/ Physical: 31-03-2011”; the physical completion date is 31-03-2011.
Completion Date: Financial: 05-07-2011/ Physical: 31-03-2011
[10]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 3
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
4.940 km
Road length 4.940 km; 4.940 km recorded as completed.
Road Length (Kms): 4.940
[7]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 3
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 3