Project record
MRL3-Chikkahosahalli to Thondebavi
PMGSY-II · package KN19139 · Gowribidanur block · Maintenance
- Location
- Gowribidanur block, Chikkaballapura district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
MRL3-Chikkahosahalli to Thondebavi
OMMAS lists PMGSY-II work KN19139 as “MRL3-Chikkahosahalli to Thondebavi”.
Road Name / Bridge Name: MRL3-Chikkahosahalli to Thondebavi
[1]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-II (CSV export), p. 1
Project / work ID
KN19139
OMMAS package number KN19139.
Package No.: KN19139
[2]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-II (CSV export), p. 1
Responsible agency
DPIU Of Chikkaballapur
The programme implementation unit is recorded as “DPIU Of Chikkaballapur”.
Programme Implementation Unit: DPIU Of Chikkaballapur
[3]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-II (CSV export), p. 1
Contractor
JAYARAM J S
OMMAS lists the contractor for this work as “JAYARAM J S”.
Contractor Name: JAYARAM J S [24 Jul 2014]
[4]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-II (CSV export), p. 1
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹282.14 lakh
The sanction cost is recorded as 282.14 (₹ lakh).
Sanction Cost: 282.14
[5]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-II (CSV export), p. 1
Maintenance cost due
₹24.13 lakh
The “5 Years Maintenance Cost Due” column shows 24.13 (₹ lakh).
5 Years Maintenance Cost Due: 24.13
[9]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-II (CSV export), p. 1
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
30-03-2015
The completion date column reads “Financial: 24-05-2016/ Physical: 30-03-2015”; the physical completion date is 30-03-2015.
Completion Date: Financial: 24-05-2016/ Physical: 30-03-2015
[10]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-II (CSV export), p. 1
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
8.250 km
Road length 8.250 km; 8.250 km recorded as completed.
Road Length (Kms): 8.250
[7]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-II (CSV export), p. 1
Stage of work
Maintenance
OMMAS records the stage of progress as “Maintenance”.
Stage of Progress: Maintenance
[8]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-II (CSV export), p. 1