MRL1-Keshwara to Melur

PMGSY-II · package KN19143 · Sidlaghatta block · Maintenance

Location
Sidlaghatta block, Chikkaballapura district
Alignment drawn
none published: found by name
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

MRL1-Keshwara to Melur

OMMAS lists PMGSY-II work KN19143 as “MRL1-Keshwara to Melur”.

Road Name / Bridge Name: MRL1-Keshwara to Melur

[1]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-II (CSV export), p. 2

VerifiedOfficial record

Project / work ID

KN19143

OMMAS package number KN19143.

VerifiedOfficial record

Responsible agency

DPIU Of Chikkaballapur

The programme implementation unit is recorded as “DPIU Of Chikkaballapur”.

Programme Implementation Unit: DPIU Of Chikkaballapur

[3]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-II (CSV export), p. 2

VerifiedOfficial record

Contractor

B.N. Devaraj

OMMAS lists the contractor for this work as “B.N. Devaraj”.

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹234.14 lakh

The sanction cost is recorded as 234.14 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹20.99 lakh

The “5 Years Maintenance Cost Due” column shows 20.99 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

29-03-2016

The completion date column reads “Financial: 20-12-2016/ Physical: 29-03-2016”; the physical completion date is 29-03-2016.

Completion Date: Financial: 20-12-2016/ Physical: 29-03-2016

[10]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-II (CSV export), p. 2

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

5.700 km

Road length 5.700 km; 5.700 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record