Project record
D.Palya - Yarranagenahalli
PMGSY-I · package KN1928 · Gowribidanur block · Completed
- Location
- Gowribidanur block, Chikkaballapura district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
D.Palya - Yarranagenahalli
OMMAS lists PMGSY-I work KN1928 as “D.Palya - Yarranagenahalli”.
Road Name / Bridge Name: D.Palya - Yarranagenahalli
[1]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 12
Project / work ID
KN1928
OMMAS package number KN1928.
Package No.: KN1928
[2]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 12
Responsible agency
DPIU Of Chikkaballapur
The programme implementation unit is recorded as “DPIU Of Chikkaballapur”.
Programme Implementation Unit: DPIU Of Chikkaballapur
[3]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 12
Contractor
Balaraju B
OMMAS lists the contractor for this work as “Balaraju B”.
Contractor Name: Balaraju B [22 May 2007]
[4]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 12
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹17.00 lakh
The sanction cost is recorded as 17.00 (₹ lakh).
Sanction Cost: 17.00
[5]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 12
Maintenance cost due
₹1.20 lakh
The “5 Years Maintenance Cost Due” column shows 1.20 (₹ lakh).
5 Years Maintenance Cost Due: 1.20
[9]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 12
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-08-2008
The completion date column reads “Financial: 29-11-2008/ Physical: 31-08-2008”; the physical completion date is 31-08-2008.
Completion Date: Financial: 29-11-2008/ Physical: 31-08-2008
[10]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 12
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
0.960 km
Road length 0.960 km; 0.960 km recorded as completed.
Road Length (Kms): 0.960
[7]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 12
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 12