Project record
Krishnarajapura - T02
PMGSY-I · package KN1968 · Gowribidanur block · Maintenance
- Location
- Gowribidanur block, Chikkaballapura district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
Krishnarajapura - T02
OMMAS lists PMGSY-I work KN1968 as “Krishnarajapura - T02”.
Road Name / Bridge Name: Krishnarajapura - T02
[1]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 13
Project / work ID
KN1968
OMMAS package number KN1968.
Package No.: KN1968
[2]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 13
Responsible agency
DPIU Of Chikkaballapur
The programme implementation unit is recorded as “DPIU Of Chikkaballapur”.
Programme Implementation Unit: DPIU Of Chikkaballapur
[3]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 13
Contractor
H S SOMESH
OMMAS lists the contractor for this work as “H S SOMESH”.
Contractor Name: H S SOMESH [30 Jan 2009]
[4]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 13
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹231.50 lakh
The sanction cost is recorded as 231.50 (₹ lakh).
Sanction Cost: 231.50
[5]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 13
Maintenance cost due
₹15.80 lakh
The “5 Years Maintenance Cost Due” column shows 15.80 (₹ lakh).
5 Years Maintenance Cost Due: 15.80
[9]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 13
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-10-2009
The completion date column reads “Financial: 09-07-2010/ Physical: 31-10-2009”; the physical completion date is 31-10-2009.
Completion Date: Financial: 09-07-2010/ Physical: 31-10-2009
[10]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 13
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
8.250 km
Road length 8.250 km; 8.250 km recorded as completed.
Road Length (Kms): 8.250
[7]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 13
Stage of work
Maintenance
OMMAS records the stage of progress as “Maintenance”.
Stage of Progress: Maintenance
[8]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 13