Project record
Arigevarigutta - T-01
PMGSY-I · package KN1972 · Bagepalli block · Completed
- Location
- Bagepalli block, Chikkaballapura district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
Arigevarigutta - T-01
OMMAS lists PMGSY-I work KN1972 as “Arigevarigutta - T-01”.
Road Name / Bridge Name: Arigevarigutta - T-01
[1]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 2
Project / work ID
KN1972
OMMAS package number KN1972.
Package No.: KN1972
[2]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 2
Responsible agency
DPIU Of Chikkaballapur
The programme implementation unit is recorded as “DPIU Of Chikkaballapur”.
Programme Implementation Unit: DPIU Of Chikkaballapur
[3]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 2
Contractor
Byrappa
OMMAS lists the contractor for this work as “Byrappa”.
Contractor Name: Byrappa [25 Feb 2009]
[4]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 2
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹200.70 lakh
The sanction cost is recorded as 200.70 (₹ lakh).
Sanction Cost: 200.70
[5]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 2
Maintenance cost due
₹14.46 lakh
The “5 Years Maintenance Cost Due” column shows 14.46 (₹ lakh).
5 Years Maintenance Cost Due: 14.46
[9]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 2
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-03-2010
The completion date column reads “Financial: 27-04-2011/ Physical: 31-03-2010”; the physical completion date is 31-03-2010.
Completion Date: Financial: 27-04-2011/ Physical: 31-03-2010
[10]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 2
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
7.550 km
Road length 7.550 km; 7.550 km recorded as completed.
Road Length (Kms): 7.550
[7]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 2
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-I (CSV export), p. 2