Project record
MRL02-Madakavaripalli to Billur
PMGSY-III · package KN3001 · Bagepalli block · Maintenance
- Location
- Bagepalli block, Chikkaballapura district
- Alignment drawn
- 18 m · official GIS
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
MRL02-Madakavaripalli to Billur
OMMAS lists PMGSY-III work KN3001 as “MRL02-Madakavaripalli to Billur”.
Road Name / Bridge Name: MRL02-Madakavaripalli to Billur
[1]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 1
Project / work ID
KN3001
OMMAS package number KN3001.
Package No.: KN3001
[2]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 1
Responsible agency
DPIU Of Chikkaballapur
The programme implementation unit is recorded as “DPIU Of Chikkaballapur”.
Programme Implementation Unit: DPIU Of Chikkaballapur
[3]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 1
Contractor
BNN Constructions Pvt Ltd
OMMAS lists the contractor for this work as “BNN Constructions Pvt Ltd”.
Contractor Name: BNN Constructions Pvt Ltd [01 Jul 2020]
[4]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 1
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹578.20 lakh
The sanction cost is recorded as 578.20 (₹ lakh).
Sanction Cost: 578.20
[5]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 1
Maintenance cost due
₹59.44 lakh
The “5 Years Maintenance Cost Due” column shows 59.44 (₹ lakh).
5 Years Maintenance Cost Due: 59.44
[9]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 1
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
12-07-2021
The completion date column reads “Financial: 04-12-2021/ Physical: 12-07-2021”; the physical completion date is 12-07-2021.
Completion Date: Financial: 04-12-2021/ Physical: 12-07-2021
[10]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 1
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
10.171 km
Road length 10.171 km; 10.171 km recorded as completed.
Road Length (Kms): 10.171
[7]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 1
Stage of work
Maintenance
OMMAS records the stage of progress as “Maintenance”.
Stage of Progress: Maintenance
[8]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 1