T01-Pathapalya to Pollanayakanahalli Via Kamsanapalli peddanagurlu

PMGSY-III · package KN3002 · Bagepalli block · Maintenance

Location
Bagepalli block, Chikkaballapura district
Alignment drawn
11 km · official GIS
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

T01-Pathapalya to Pollanayakanahalli Via Kamsanapalli peddanagurlu

OMMAS lists PMGSY-III work KN3002 as “T01-Pathapalya to Pollanayakanahalli Via Kamsanapalli peddanagurlu”.

Road Name / Bridge Name: T01-Pathapalya to Pollanayakanahalli Via Kamsanapalli peddanagurlu

[1]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Project / work ID

KN3002

OMMAS package number KN3002.

VerifiedOfficial record

Responsible agency

DPIU Of Chikkaballapur

The programme implementation unit is recorded as “DPIU Of Chikkaballapur”.

Programme Implementation Unit: DPIU Of Chikkaballapur

[3]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Contractor

K.N Channakeshava

OMMAS lists the contractor for this work as “K.N Channakeshava”.

Contractor Name: K.N Channakeshava [01 Jul 2020]

[4]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹880.85 lakh

The sanction cost is recorded as 880.85 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹85.72 lakh

The “5 Years Maintenance Cost Due” column shows 85.72 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

16-08-2023

The completion date column reads “Financial: 08-02-2024/ Physical: 16-08-2023”; the physical completion date is 16-08-2023.

Completion Date: Financial: 08-02-2024/ Physical: 16-08-2023

[10]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

15.272 km

Road length 15.272 km; 13.770 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record