MRL04-From NH to B.B.Road via Yarralakkenahalli, Bhogenahalli, Thirumani, Katenahalli, Mittemari Road

PMGSY-III · package KN3008 · Gudibanda block · Maintenance

Location
Gudibanda block, Chikkaballapura district
Alignment drawn
7.3 km · official GIS
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

OMMAS lists PMGSY-III work KN3008 as “MRL04-From NH to B.B.Road via Yarralakkenahalli, Bhogenahalli, Thirumani, Katenahalli, Mittemari Road”.

Road Name / Bridge Name: MRL04-From NH to B.B.Road via Yarralakkenahalli, Bhogenahalli, Thirumani, Katenahalli, Mittemari Road

[1]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 3

VerifiedOfficial record

Project / work ID

KN3008

OMMAS package number KN3008.

VerifiedOfficial record

Responsible agency

DPIU Of Chikkaballapur

The programme implementation unit is recorded as “DPIU Of Chikkaballapur”.

Programme Implementation Unit: DPIU Of Chikkaballapur

[3]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 3

VerifiedOfficial record

Contractor

SRI HARI CONSTRUCTIONS [01 Jul 2020], BNN Constructions Pvt Ltd

OMMAS lists the contractor for this work as “SRI HARI CONSTRUCTIONS [01 Jul 2020], BNN Constructions Pvt Ltd”.

Contractor Name: SRI HARI CONSTRUCTIONS [01 Jul 2020], BNN Constructions Pvt Ltd [13 Apr 2022]

[4]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 3

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹514.29 lakh

The sanction cost is recorded as 514.29 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹55.89 lakh

The “5 Years Maintenance Cost Due” column shows 55.89 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

13-03-2023

The completion date column reads “Financial: 31-12-2024/ Physical: 13-03-2023”; the physical completion date is 13-03-2023.

Completion Date: Financial: 31-12-2024/ Physical: 13-03-2023

[10]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 3

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

9.668 km

Road length 9.668 km; 9.670 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record