Skip to content
CivicProof

Project record

MRL14-Kachihalli to Vishwanathapura via Chikkapura Anur

PMGSY-III · package KN3009 · Chinthamani block · Maintenance

Location
Chinthamani block, Chikkaballapura district
Alignment drawn
82 m · official GIS
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

MRL14-Kachihalli to Vishwanathapura via Chikkapura Anur

OMMAS lists PMGSY-III work KN3009 as “MRL14-Kachihalli to Vishwanathapura via Chikkapura Anur”.

Road Name / Bridge Name: MRL14-Kachihalli to Vishwanathapura via Chikkapura Anur

[1]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 2

VerifiedOfficial record

Project / work ID

KN3009

OMMAS package number KN3009.

VerifiedOfficial record

Responsible agency

DPIU Of Chikkaballapur

The programme implementation unit is recorded as “DPIU Of Chikkaballapur”.

Programme Implementation Unit: DPIU Of Chikkaballapur

[3]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 2

VerifiedOfficial record

Contractor

K V Sathyanararayana Reddy

OMMAS lists the contractor for this work as “K V Sathyanararayana Reddy”.

Contractor Name: K V Sathyanararayana Reddy [01 Jul 2020]

[4]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 2

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹442.71 lakh

The sanction cost is recorded as 442.71 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹45.95 lakh

The “5 Years Maintenance Cost Due” column shows 45.95 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

01-06-2021

The completion date column reads “Financial: 29-09-2021/ Physical: 01-06-2021”; the physical completion date is 01-06-2021.

Completion Date: Financial: 29-09-2021/ Physical: 01-06-2021

[10]SLR: Statewise List of Works — Karnataka, Chikkaballapura, PMGSY-III (CSV export), p. 2

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

8.500 km

Road length 8.500 km; 8.400 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record