T02-Chikkabanavara (SH-02) to Nagadasanahalli Via Ganigarahalli, Kasaghattapura, Mylappanahalli, Madappanahalli, Itgalapura, Adde, Sadenahalli, Adiganahalli and Rajanukunte

PMGSY-III road upgrade KN03-62, 19.730 km, in its 5-year maintenance stage.

Location
Bangalore(N) block, Bengaluru Urban district
Alignment drawn
20 km · official GIS
Documents
3
Verified facts
11 of 11
11 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

OMMAS lists PMGSY-III work KN03-62 as “T02-Chikkabanavara (SH-02) to Nagadasanahalli Via Ganigarahalli, Kasaghattapura, Mylappanahalli, Madappanahalli, Itgalapura, Adde, Sadenahalli, Adiganahalli and Rajanukunte”, an upgrade sanctioned in 2019-2020.

Bangalore(N) KN03-62 2019 - 2020 ROAD T02-Chikkabanavara (SH-02) to Nagadasanahalli Via Ganigarahalli, Kasaghattapura, Mylappanahalli, Madappanahalli, Itgalapura, Adde, Sadenahalli, Adiganahalli and Rajanukunte

[1]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3

VerifiedOfficial record

Project / work ID

KN03-62

OMMAS package number KN03-62.

Bangalore(N) KN03-62 2019 - 2020 ROAD T02-Chikkabanavara (SH-02) to Nagadasanahalli Via Ganigarahalli, Kasaghattapura,…

[1]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3

VerifiedOfficial record

Responsible agency

DPIU Of Bangalore u

The programme implementation unit is recorded as “DPIU Of Bangalore u” (District Programme Implementation Unit, PMGSY, Bengaluru Urban).

8 Bangalore U DPIU Of Bangalore u Bangalore(N) KN03-62

[2]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3

VerifiedOfficial record

Contractor

M/s. Ganesh Enterprises

OMMAS lists the contractor as “M/s. Ganesh Enterprises Sri K B Ramesh”.

1,617.40 671.12 19.730 0.000 21.700 1,486.90 Maintenance Regular PMGSY M/s. Ganesh Enterprises Sri K B Ramesh [04 Sep 2020]

[3]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹1,617.40 lakh

The sanction cost is recorded as 1,617.40 (₹ lakh); expenditure to date is 1,486.90 lakh.

1,617.40 671.12 19.730 0.000 21.700 1,486.90

[4]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3

VerifiedOfficial record

Maintenance cost due

₹116.15 lakh

The “5 Years Maintenance Cost Due” column shows 116.15 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

17-03-2023

The completion date column reads “Financial: 01-07-2024 / Physical: 17-03-2023”; the physical completion date is 17-03-2023.

116.15 Financial: 01-07 -2024/ Physical: 17-03-2023

[8]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[9]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

19.730 km

Upgrade of a 19.730 km road; 21.700 km recorded as completed.

1,617.40 671.12 19.730 0.000 21.700 1,486.90

[4]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

1,617.40 671.12 19.730 0.000 21.700 1,486.90 Maintenance Regular PMGSY

[6]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3

VerifiedOfficial record

Quality inspection

Required Improvement

Quality monitoring, Jan 2021 to Sep 2026: 3 National Quality Monitor inspections, last graded “Required Improvement”; 10 State Quality Monitor inspections, last graded “Satisfactory”.

…Mylappanahalli, Madappanahalli, Itgalapura, Adde, Sadenahalli, Adiganahalli and Rajanukunte 19.730 3 Required Improvement 10 Satisfactory

[10]Works Wise Grading Abstract — NQM/SQM inspections, Bangalore U, Jan 2021 to Sep 2026, p. 2

VerifiedOfficial record