Project record
T02-Chikkabanavara (SH-02) to Nagadasanahalli Via Ganigarahalli, Kasaghattapura, Mylappanahalli, Madappanahalli, Itgalapura, Adde, Sadenahalli, Adiganahalli and Rajanukunte
PMGSY-III road upgrade KN03-62, 19.730 km, in its 5-year maintenance stage.
- Location
- Bangalore(N) block, Bengaluru Urban district
- Alignment drawn
- 20 km · official GIS
- Documents
- 3
- Verified facts
- 11 of 11
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
OMMAS lists PMGSY-III work KN03-62 as “T02-Chikkabanavara (SH-02) to Nagadasanahalli Via Ganigarahalli, Kasaghattapura, Mylappanahalli, Madappanahalli, Itgalapura, Adde, Sadenahalli, Adiganahalli and Rajanukunte”, an upgrade sanctioned in 2019-2020.
Bangalore(N) KN03-62 2019 - 2020 ROAD T02-Chikkabanavara (SH-02) to Nagadasanahalli Via Ganigarahalli, Kasaghattapura, Mylappanahalli, Madappanahalli, Itgalapura, Adde, Sadenahalli, Adiganahalli and Rajanukunte
[1]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3
Project / work ID
KN03-62
OMMAS package number KN03-62.
Bangalore(N) KN03-62 2019 - 2020 ROAD T02-Chikkabanavara (SH-02) to Nagadasanahalli Via Ganigarahalli, Kasaghattapura,…
[1]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3
Responsible agency
DPIU Of Bangalore u
The programme implementation unit is recorded as “DPIU Of Bangalore u” (District Programme Implementation Unit, PMGSY, Bengaluru Urban).
8 Bangalore U DPIU Of Bangalore u Bangalore(N) KN03-62
[2]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3
Contractor
M/s. Ganesh Enterprises
OMMAS lists the contractor as “M/s. Ganesh Enterprises Sri K B Ramesh”.
1,617.40 671.12 19.730 0.000 21.700 1,486.90 Maintenance Regular PMGSY M/s. Ganesh Enterprises Sri K B Ramesh [04 Sep 2020]
[3]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹1,617.40 lakh
The sanction cost is recorded as 1,617.40 (₹ lakh); expenditure to date is 1,486.90 lakh.
1,617.40 671.12 19.730 0.000 21.700 1,486.90
[4]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3
Maintenance cost due
₹116.15 lakh
The “5 Years Maintenance Cost Due” column shows 116.15 (₹ lakh).
116.15 Financial: 01-07 -2024
[7]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
17-03-2023
The completion date column reads “Financial: 01-07-2024 / Physical: 17-03-2023”; the physical completion date is 17-03-2023.
116.15 Financial: 01-07 -2024/ Physical: 17-03-2023
[8]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[9]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
19.730 km
Upgrade of a 19.730 km road; 21.700 km recorded as completed.
1,617.40 671.12 19.730 0.000 21.700 1,486.90
[4]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3
Stage of work
Maintenance
OMMAS records the stage of progress as “Maintenance”.
1,617.40 671.12 19.730 0.000 21.700 1,486.90 Maintenance Regular PMGSY
[6]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 3
Quality inspection
Required Improvement
Quality monitoring, Jan 2021 to Sep 2026: 3 National Quality Monitor inspections, last graded “Required Improvement”; 10 State Quality Monitor inspections, last graded “Satisfactory”.
…Mylappanahalli, Madappanahalli, Itgalapura, Adde, Sadenahalli, Adiganahalli and Rajanukunte 19.730 3 Required Improvement 10 Satisfactory
[10]Works Wise Grading Abstract — NQM/SQM inspections, Bangalore U, Jan 2021 to Sep 2026, p. 2