Project record
MRL12-Tharalu To Kaggalipura- Bannerughatta Road Via Thataguppe,Alakabelalu And Gutte palya.
PMGSY-III road upgrade KN03-65, 6.260 km, in its 5-year maintenance stage.
- Location
- Bangalore(S) block, Bengaluru Urban district
- Alignment drawn
- 6.3 km · official GIS
- Documents
- 3
- Verified facts
- 11 of 11
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
OMMAS lists PMGSY-III work KN03-65 as “MRL12-Tharalu To Kaggalipura- Bannerughatta Road Via Thataguppe,Alakabelalu And Gutte palya.”, an upgrade sanctioned in 2019-2020.
Bangalore(S) KN03-65 2019 - 2020 ROAD MRL12-Tharalu To Kaggalipura- Bannerughatta Road Via Thataguppe,Alakabelalu And Gutte palya.
[1]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 4
Project / work ID
KN03-65
OMMAS package number KN03-65.
Bangalore(S) KN03-65 2019 - 2020 ROAD MRL12-Tharalu To Kaggalipura- Bannerughatta Road Via Thataguppe,Alakabelalu And Gutte palya.
[1]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 4
Responsible agency
DPIU Of Bangalore u
The programme implementation unit is recorded as “DPIU Of Bangalore u” (District Programme Implementation Unit, PMGSY, Bengaluru Urban).
10 Bangalore U DPIU Of Bangalore u Bangalore(S) KN03-65
[2]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 4
Contractor
K.C Shivaram
OMMAS lists the contractor for this work as “K.C Shivaram”.
494.71 205.38 6.260 0.000 5.650 425.36 Maintenance Regular PMGSY K.C Shivaram [08 Jul 2020]
[3]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 4
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹494.71 lakh
The sanction cost is recorded as 494.71 (₹ lakh); expenditure to date is 425.36 lakh.
494.71 205.38 6.260 0.000 5.650 425.36
[4]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 4
Maintenance cost due
₹36.85 lakh
The “5 Years Maintenance Cost Due” column shows 36.85 (₹ lakh).
36.85 Financial: 16-03 -2024
[7]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 4
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
09-10-2023
The completion date column reads “Financial: 16-03-2024 / Physical: 09-10-2023”; the physical completion date is 09-10-2023.
36.85 Financial: 16-03 -2024/ Physical: 09-10-2023
[8]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 4
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[9]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
6.260 km
Upgrade of a 6.260 km road; 5.650 km recorded as completed.
494.71 205.38 6.260 0.000 5.650 425.36
[4]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 4
Stage of work
Maintenance
OMMAS records the stage of progress as “Maintenance”.
494.71 205.38 6.260 0.000 5.650 425.36 Maintenance Regular PMGSY
[6]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 4
Quality inspection
Satisfactory
Quality monitoring, Jan 2021 to Sep 2026: 2 National Quality Monitor inspections, last graded “Satisfactory”; 8 State Quality Monitor inspections, last graded “Satisfactory”.
KN03-65 MRL12-Tharalu To Kaggalipura- Bannerughatta Road Via Thataguppe,Alakabelalu And Gutte palya. 6.260 2 Satisfactory 8 Satisfactory
[10]Works Wise Grading Abstract — NQM/SQM inspections, Bangalore U, Jan 2021 to Sep 2026, p. 2