Project record
MRL04-NH 07 (Chandapura) to SH 35 (Attibele) via Lakshmisagara, Allibommasandra, Guddahatti and Jigala
PMGSY-III road upgrade KN03-67, 7.420 km, in its 5-year maintenance stage.
- Location
- Anekal block, Bengaluru Urban district
- Alignment drawn
- 7.4 km · official GIS
- Documents
- 3
- Verified facts
- 11 of 11
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
OMMAS lists PMGSY-III work KN03-67 as “MRL04-NH 07 (Chandapura) to SH 35 (Attibele) via Lakshmisagara, Allibommasandra, Guddahatti and Jigala”, an upgrade sanctioned in 2019-2020.
Anekal KN03-67 2019 - 2020 ROAD MRL04-NH 07 (Chandapura) to SH 35 (Attibele) via Lakshmisagara, Allibommasandra, Guddahatti and Jigala
[1]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Project / work ID
KN03-67
OMMAS package number KN03-67.
Anekal KN03-67 2019 - 2020 ROAD MRL04-NH 07 (Chandapura) to SH 35 (Attibele) via Lakshmisagara, Allibommasandra, Guddahatti…
[1]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Responsible agency
DPIU Of Bangalore u
The programme implementation unit is recorded as “DPIU Of Bangalore u” (District Programme Implementation Unit, PMGSY, Bengaluru Urban).
1 Bangalore U DPIU Of Bangalore u Anekal KN03-67
[2]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Contractor
Prakash Reddy V
OMMAS lists the contractor for this work as “Prakash Reddy V”.
614.39 249.99 7.420 0.000 5.710 510.64 Maintenance Regular PMGSY Prakash Reddy V [08 Jul 2020]
[3]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹614.39 lakh
The sanction cost is recorded as 614.39 (₹ lakh); expenditure to date is 510.64 lakh.
614.39 249.99 7.420 0.000 5.710 510.64
[4]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Maintenance cost due
₹44.45 lakh
The “5 Years Maintenance Cost Due” column shows 44.45 (₹ lakh).
44.45 Financial: 25-02 -2026
[7]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
10-12-2025
The completion date column reads “Financial: 25-02-2026 / Physical: 10-12-2025”; the physical completion date is 10-12-2025. Only 5.710 of 7.420 km is recorded as completed.
44.45 Financial: 25-02 -2026/ Physical: 10-12-2025
[8]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[9]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
7.420 km
Upgrade of a 7.420 km road; 5.710 km recorded as completed.
614.39 249.99 7.420 0.000 5.710 510.64
[4]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Stage of work
Maintenance
OMMAS records the stage of progress as “Maintenance”.
614.39 249.99 7.420 0.000 5.710 510.64 Maintenance Regular PMGSY
[6]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Quality inspection
Satisfactory
Quality monitoring, Jan 2021 to Sep 2026: 3 National Quality Monitor inspections, last graded “Satisfactory”; 4 State Quality Monitor inspections, last graded “Satisfactory”.
…07 (Chandapura) to SH 35 (Attibele) via Lakshmisagara, Allibommasandra, Guddahatti and Jigala 7.420 3 Satisfactory 4 Satisfactory
[10]Works Wise Grading Abstract — NQM/SQM inspections, Bangalore U, Jan 2021 to Sep 2026, p. 1