Project record
MRL11-Kodathi to Sulikunte Colony,Mullur Colony,Mullur Kachamaranahalli
PMGSY-III road upgrade KN03-70, 4.250 km, in its 5-year maintenance stage.
- Location
- Bangalore(E) block, Bengaluru Urban district
- Alignment drawn
- 4.3 km · official GIS
- Documents
- 3
- Verified facts
- 11 of 11
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
MRL11-Kodathi to Sulikunte Colony,Mullur Colony,Mullur Kachamaranahalli
OMMAS lists PMGSY-III work KN03-70 as “MRL11-Kodathi to Sulikunte Colony,Mullur Colony,Mullur Kachamaranahalli”, an upgrade sanctioned in 2019-2020.
Bangalore(E) KN03-70 2019 - 2020 ROAD MRL11-Kodathi to Sulikunte Colony,Mullur Colony,Mullur Kachamaranahalli
[1]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Project / work ID
KN03-70
OMMAS package number KN03-70.
Bangalore(E) KN03-70 2019 - 2020 ROAD MRL11-Kodathi to Sulikunte Colony,Mullur Colony,Mullur Kachamaranahalli
[1]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Responsible agency
DPIU Of Bangalore u
The programme implementation unit is recorded as “DPIU Of Bangalore u” (District Programme Implementation Unit, PMGSY, Bengaluru Urban).
5 Bangalore U DPIU Of Bangalore u Bangalore(E) KN03-70
[2]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Contractor
Venkatarama Reddy .M
OMMAS lists the contractor for this work as “Venkatarama Reddy .M”.
364.29 152.84 4.250 0.000 4.250 268.89 Maintenance Regular PMGSY Venkatarama Reddy .M [29 Jun 2020]
[3]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹364.29 lakh
The sanction cost is recorded as 364.29 (₹ lakh); expenditure to date is 268.89 lakh.
364.29 152.84 4.250 0.000 4.250 268.89
[4]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Maintenance cost due
₹36.49 lakh
The “5 Years Maintenance Cost Due” column shows 36.49 (₹ lakh).
36.49 Financial: 27-05 -2024
[7]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
05-03-2022
The completion date column reads “Financial: 27-05-2024 / Physical: 05-03-2022”; the physical completion date is 05-03-2022.
36.49 Financial: 27-05 -2024/ Physical: 05-03-2022
[8]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[9]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
4.250 km
Upgrade of a 4.250 km road; 4.250 km recorded as completed.
364.29 152.84 4.250 0.000 4.250 268.89
[4]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Stage of work
Maintenance
OMMAS records the stage of progress as “Maintenance”.
364.29 152.84 4.250 0.000 4.250 268.89 Maintenance Regular PMGSY
[6]SLR: Statewise List of Works — Karnataka, Bangalore U, PMGSY-III, p. 1
Quality inspection
Satisfactory
Quality monitoring, Jan 2021 to Sep 2026: 1 National Quality Monitor inspection, last graded “Satisfactory”; 3 State Quality Monitor inspections, last graded “Satisfactory”.
KN03-70 MRL11-Kodathi to Sulikunte Colony,Mullur Colony,Mullur Kachamaranahalli 4.250 1 Satisfactory 3 Satisfactory
[10]Works Wise Grading Abstract — NQM/SQM inspections, Bangalore U, Jan 2021 to Sep 2026, p. 1