Skip to content
CivicProof

Project record

KGF-Kamasamudram road to Doddabommapalli

PMGSY-I · package KN1901 · Bangarpet block · Completed

Location
Bangarpet block, Kolar district
Alignment drawn
none published: found by name
Documents
2
Verified facts
9 of 9
9 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

KGF-Kamasamudram road to Doddabommapalli

OMMAS lists PMGSY-I work KN1901 as “KGF-Kamasamudram road to Doddabommapalli”.

Road Name / Bridge Name: KGF-Kamasamudram road to Doddabommapalli

[1]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 1

VerifiedOfficial record

Project / work ID

KN1901

OMMAS package number KN1901.

VerifiedOfficial record

Responsible agency

DPIU Of Kolar

The programme implementation unit is recorded as “DPIU Of Kolar”.

Programme Implementation Unit: DPIU Of Kolar

[3]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 1

VerifiedOfficial record

Contractor

Karnataka Land Army Corporation

OMMAS lists the contractor for this work as “Karnataka Land Army Corporation”.

Contractor Name: Karnataka Land Army Corporation [26 Nov 2001]

[4]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 1

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹24.94 lakh

The sanction cost is recorded as 24.94 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

31-03-2003

The completion date column reads “Financial: 01-04-2005/ Physical: 31-03-2003”; the physical completion date is 31-03-2003.

Completion Date: Financial: 01-04-2005/ Physical: 31-03-2003

[9]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 1

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[10]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

3.500 km

Road length 3.500 km; 3.500 km recorded as completed.

VerifiedOfficial record

Stage of work

Completed

OMMAS records the stage of progress as “Completed”.

VerifiedOfficial record