Project record
Byrakur to Chikkanagavara
PMGSY-I · package KN1904 · Mulbagal block · Completed
- Location
- Mulbagal block, Kolar district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 9 of 9
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
Byrakur to Chikkanagavara
OMMAS lists PMGSY-I work KN1904 as “Byrakur to Chikkanagavara”.
Road Name / Bridge Name: Byrakur to Chikkanagavara
[1]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 12
Project / work ID
KN1904
OMMAS package number KN1904.
Package No.: KN1904
[2]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 12
Responsible agency
DPIU Of Kolar
The programme implementation unit is recorded as “DPIU Of Kolar”.
Programme Implementation Unit: DPIU Of Kolar
[3]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 12
Contractor
V Krishna Reddy
OMMAS lists the contractor for this work as “V Krishna Reddy”.
Contractor Name: V Krishna Reddy [23 Oct 2002]
[4]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 12
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹72.05 lakh
The sanction cost is recorded as 72.05 (₹ lakh).
Sanction Cost: 72.05
[5]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 12
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-03-2006
The completion date column reads “Financial: 31-03-2006/ Physical: 31-03-2006”; the physical completion date is 31-03-2006.
Completion Date: Financial: 31-03-2006/ Physical: 31-03-2006
[9]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 12
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[10]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
6.260 km
Road length 6.260 km; 6.260 km recorded as completed.
Road Length (Kms): 6.260
[7]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 12
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 12