Project record
MRL4-Bedisettihalli to Dinnahalli
PMGSY-II · package KN19131 · Malur block · Maintenance
- Location
- Malur block, Kolar district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
MRL4-Bedisettihalli to Dinnahalli
OMMAS lists PMGSY-II work KN19131 as “MRL4-Bedisettihalli to Dinnahalli”.
Road Name / Bridge Name: MRL4-Bedisettihalli to Dinnahalli
[1]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-II (CSV export), p. 2
Project / work ID
KN19131
OMMAS package number KN19131.
Package No.: KN19131
[2]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-II (CSV export), p. 2
Responsible agency
DPIU Of Kolar
The programme implementation unit is recorded as “DPIU Of Kolar”.
Programme Implementation Unit: DPIU Of Kolar
[3]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-II (CSV export), p. 2
Contractor
M N CHANDRASHEKARAIAH
OMMAS lists the contractor for this work as “M N CHANDRASHEKARAIAH”.
Contractor Name: M N CHANDRASHEKARAIAH [28 Feb 2014]
[4]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-II (CSV export), p. 2
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹275.58 lakh
The sanction cost is recorded as 275.58 (₹ lakh).
Sanction Cost: 275.58
[5]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-II (CSV export), p. 2
Maintenance cost due
₹20.94 lakh
The “5 Years Maintenance Cost Due” column shows 20.94 (₹ lakh).
5 Years Maintenance Cost Due: 20.94
[9]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-II (CSV export), p. 2
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-03-2015
The completion date column reads “Financial: 06-12-2016/ Physical: 31-03-2015”; the physical completion date is 31-03-2015.
Completion Date: Financial: 06-12-2016/ Physical: 31-03-2015
[10]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-II (CSV export), p. 2
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
7.160 km
Road length 7.160 km; 7.160 km recorded as completed.
Road Length (Kms): 7.160
[7]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-II (CSV export), p. 2
Stage of work
Maintenance
OMMAS records the stage of progress as “Maintenance”.
Stage of Progress: Maintenance
[8]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-II (CSV export), p. 2