Project record

MRL09-Kolar Taluk Border to Yalavaguli

PMGSY-III · package KN19153 · Malur block · Maintenance

Location
Malur block, Kolar district
Alignment drawn
5.5 km · official GIS
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

MRL09-Kolar Taluk Border to Yalavaguli

OMMAS lists PMGSY-III work KN19153 as “MRL09-Kolar Taluk Border to Yalavaguli”.

Road Name / Bridge Name: MRL09-Kolar Taluk Border to Yalavaguli

[1]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-III (CSV export), p. 2

VerifiedOfficial record

Project / work ID

KN19153

OMMAS package number KN19153.

VerifiedOfficial record

Responsible agency

DPIU Of Kolar

The programme implementation unit is recorded as “DPIU Of Kolar”.

Programme Implementation Unit: DPIU Of Kolar

[3]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-III (CSV export), p. 2

VerifiedOfficial record

Contractor

A.G Narayanaswamy & Co

OMMAS lists the contractor for this work as “A.G Narayanaswamy & Co”.

Contractor Name: A.G Narayanaswamy & Co [03 Sep 2020]

[4]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-III (CSV export), p. 2

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹586.00 lakh

The sanction cost is recorded as 586.00 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹31.15 lakh

The “5 Years Maintenance Cost Due” column shows 31.15 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

31-03-2022

The completion date column reads “Financial: 31-03-2023/ Physical: 31-03-2022”; the physical completion date is 31-03-2022.

Completion Date: Financial: 31-03-2023/ Physical: 31-03-2022

[10]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-III (CSV export), p. 2

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

8.852 km

Road length 8.852 km; 8.852 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record