Project record

MRL08-Harapanayakanahalli Cross to Agara

PMGSY-III · package KN19157 · Mulbagal block · Maintenance

Location
Mulbagal block, Kolar district
Alignment drawn
7.4 km · official GIS
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

MRL08-Harapanayakanahalli Cross to Agara

OMMAS lists PMGSY-III work KN19157 as “MRL08-Harapanayakanahalli Cross to Agara”.

Road Name / Bridge Name: MRL08-Harapanayakanahalli Cross to Agara

[1]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-III (CSV export), p. 3

VerifiedOfficial record

Project / work ID

KN19157

OMMAS package number KN19157.

VerifiedOfficial record

Responsible agency

DPIU Of Kolar

The programme implementation unit is recorded as “DPIU Of Kolar”.

Programme Implementation Unit: DPIU Of Kolar

[3]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-III (CSV export), p. 3

VerifiedOfficial record

Contractor

BMC Gowda Constructions

OMMAS lists the contractor for this work as “BMC Gowda Constructions”.

Contractor Name: BMC Gowda Constructions [22 Jul 2020]

[4]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-III (CSV export), p. 3

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹385.05 lakh

The sanction cost is recorded as 385.05 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹35.73 lakh

The “5 Years Maintenance Cost Due” column shows 35.73 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

23-12-2021

The completion date column reads “Financial: 26-03-2022/ Physical: 23-12-2021”; the physical completion date is 23-12-2021.

Completion Date: Financial: 26-03-2022/ Physical: 23-12-2021

[10]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-III (CSV export), p. 3

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

7.360 km

Road length 7.360 km; 7.360 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record