Project record

T15-SP Road to LP Road via Kornahalli, Pataballapalli, Tantharlapalli, Chennapalli, Bachivaripalli, Ganganagaripalli

PMGSY-III · package KN19164 · Srinivasapura block · Maintenance

Location
Srinivasapura block, Kolar district
Alignment drawn
3.7 km · official GIS
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

OMMAS lists PMGSY-III work KN19164 as “T15-SP Road to LP Road via Kornahalli, Pataballapalli, Tantharlapalli, Chennapalli, Bachivaripalli, Ganganagaripalli”.

Road Name / Bridge Name: T15-SP Road to LP Road via Kornahalli, Pataballapalli, Tantharlapalli, Chennapalli, Bachivaripalli, Ganganagaripalli

[1]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-III (CSV export), p. 4

VerifiedOfficial record

Project / work ID

KN19164

OMMAS package number KN19164.

VerifiedOfficial record

Responsible agency

DPIU Of Kolar

The programme implementation unit is recorded as “DPIU Of Kolar”.

Programme Implementation Unit: DPIU Of Kolar

[3]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-III (CSV export), p. 4

VerifiedOfficial record

Contractor

K V Sathyanararayana Reddy

OMMAS lists the contractor for this work as “K V Sathyanararayana Reddy”.

Contractor Name: K V Sathyanararayana Reddy [20 Jul 2020]

[4]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-III (CSV export), p. 4

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹506.57 lakh

The sanction cost is recorded as 506.57 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹44.48 lakh

The “5 Years Maintenance Cost Due” column shows 44.48 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

03-09-2021

The completion date column reads “Financial: 23-12-2021/ Physical: 03-09-2021”; the physical completion date is 03-09-2021.

Completion Date: Financial: 23-12-2021/ Physical: 03-09-2021

[10]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-III (CSV export), p. 4

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

9.570 km

Road length 9.570 km; 9.570 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record