Project record
Tayalur - A P Border via Doolapalli, Yalachepalli, byrasandra
PMGSY-I · package KN1927C · Mulbagal block · Completed
- Location
- Mulbagal block, Kolar district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
Tayalur - A P Border via Doolapalli, Yalachepalli, byrasandra
OMMAS lists PMGSY-I work KN1927C as “Tayalur - A P Border via Doolapalli, Yalachepalli, byrasandra”.
Road Name / Bridge Name: Tayalur - A P Border via Doolapalli, Yalachepalli, byrasandra
[1]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Project / work ID
KN1927C
OMMAS package number KN1927C.
Package No.: KN1927C
[2]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Responsible agency
DPIU Of Kolar
The programme implementation unit is recorded as “DPIU Of Kolar”.
Programme Implementation Unit: DPIU Of Kolar
[3]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Contractor
V. Govindappa
OMMAS lists the contractor for this work as “V. Govindappa”.
Contractor Name: V. Govindappa [19 Nov 2008]
[4]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹45.76 lakh
The sanction cost is recorded as 45.76 (₹ lakh).
Sanction Cost: 45.76
[5]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Maintenance cost due
₹3.88 lakh
The “5 Years Maintenance Cost Due” column shows 3.88 (₹ lakh).
5 Years Maintenance Cost Due: 3.88
[9]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-03-2010
The completion date column reads “Financial: 21-07-2011/ Physical: 31-03-2010”; the physical completion date is 31-03-2010.
Completion Date: Financial: 21-07-2011/ Physical: 31-03-2010
[10]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
3.120 km
Road length 3.120 km; 3.120 km recorded as completed.
Road Length (Kms): 3.120
[7]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13