Project record
Muduvadi-Kothmangala road - Uthanur via Pombarahalli, Shivanarahalli
PMGSY-I · package KN1927D · Mulbagal block · Completed
- Location
- Mulbagal block, Kolar district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
Muduvadi-Kothmangala road - Uthanur via Pombarahalli, Shivanarahalli
OMMAS lists PMGSY-I work KN1927D as “Muduvadi-Kothmangala road - Uthanur via Pombarahalli, Shivanarahalli”.
Road Name / Bridge Name: Muduvadi-Kothmangala road - Uthanur via Pombarahalli, Shivanarahalli
[1]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Project / work ID
KN1927D
OMMAS package number KN1927D.
Package No.: KN1927D
[2]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Responsible agency
DPIU Of Kolar
The programme implementation unit is recorded as “DPIU Of Kolar”.
Programme Implementation Unit: DPIU Of Kolar
[3]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Contractor
B M Chandre Gowda
OMMAS lists the contractor for this work as “B M Chandre Gowda”.
Contractor Name: B M Chandre Gowda [10 Dec 2008]
[4]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹16.89 lakh
The sanction cost is recorded as 16.89 (₹ lakh).
Sanction Cost: 16.89
[5]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Maintenance cost due
₹1.25 lakh
The “5 Years Maintenance Cost Due” column shows 1.25 (₹ lakh).
5 Years Maintenance Cost Due: 1.25
[9]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-03-2009
The completion date column reads “Financial: 23-12-2009/ Physical: 31-03-2009”; the physical completion date is 31-03-2009.
Completion Date: Financial: 23-12-2009/ Physical: 31-03-2009
[10]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
1.000 km
Road length 1.000 km; 1.000 km recorded as completed.
Road Length (Kms): 1.000
[7]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 13