Bangarapet-Budikote road - Bangarapet via Inorahosahally

PMGSY-I · package KN1940 · Bangarpet block · Completed

Location
Bangarpet block, Kolar district
Alignment drawn
none published: found by name
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

Bangarapet-Budikote road - Bangarapet via Inorahosahally

OMMAS lists PMGSY-I work KN1940 as “Bangarapet-Budikote road - Bangarapet via Inorahosahally”.

Road Name / Bridge Name: Bangarapet-Budikote road - Bangarapet via Inorahosahally

[1]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 3

VerifiedOfficial record

Project / work ID

KN1940

OMMAS package number KN1940.

VerifiedOfficial record

Responsible agency

DPIU Of Kolar

The programme implementation unit is recorded as “DPIU Of Kolar”.

Programme Implementation Unit: DPIU Of Kolar

[3]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 3

VerifiedOfficial record

Contractor

Umesh Patil

OMMAS lists the contractor for this work as “Umesh Patil”.

Contractor Name: Umesh Patil [11 Dec 2007]

[4]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 3

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹257.60 lakh

The sanction cost is recorded as 257.60 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹17.23 lakh

The “5 Years Maintenance Cost Due” column shows 17.23 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

31-03-2009

The completion date column reads “Financial: 08-06-2009/ Physical: 31-03-2009”; the physical completion date is 31-03-2009.

Completion Date: Financial: 08-06-2009/ Physical: 31-03-2009

[10]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 3

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

11.500 km

Road length 11.500 km; 11.500 km recorded as completed.

VerifiedOfficial record

Stage of work

Completed

OMMAS records the stage of progress as “Completed”.

VerifiedOfficial record