Project record
CRF Road - Yalavakunte via Nambihalli
PMGSY-I · package KN1951 · Srinivasapura block · Completed
- Location
- Srinivasapura block, Kolar district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
CRF Road - Yalavakunte via Nambihalli
OMMAS lists PMGSY-I work KN1951 as “CRF Road - Yalavakunte via Nambihalli”.
Road Name / Bridge Name: CRF Road - Yalavakunte via Nambihalli
[1]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 17
Project / work ID
KN1951
OMMAS package number KN1951.
Package No.: KN1951
[2]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 17
Responsible agency
DPIU Of Kolar
The programme implementation unit is recorded as “DPIU Of Kolar”.
Programme Implementation Unit: DPIU Of Kolar
[3]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 17
Contractor
V Krishna Reddy
OMMAS lists the contractor for this work as “V Krishna Reddy”.
Contractor Name: V Krishna Reddy [21 May 2007]
[4]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 17
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹292.00 lakh
The sanction cost is recorded as 292.00 (₹ lakh).
Sanction Cost: 292.00
[5]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 17
Maintenance cost due
₹21.53 lakh
The “5 Years Maintenance Cost Due” column shows 21.53 (₹ lakh).
5 Years Maintenance Cost Due: 21.53
[9]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 17
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-03-2009
The completion date column reads “Financial: 05-06-2010/ Physical: 31-03-2009”; the physical completion date is 31-03-2009.
Completion Date: Financial: 05-06-2010/ Physical: 31-03-2009
[10]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 17
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
14.370 km
Road length 14.370 km; 14.370 km recorded as completed.
Road Length (Kms): 14.370
[7]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 17
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Kolar, PMGSY-I (CSV export), p. 17