Bannigiri to Kanakapura Tq. Border via Gollahalli Chennammanapalya

PMGSY-I · package KN0202 · Ramanagar block · Completed

Location
Ramanagar block, Ramanagara (Bengaluru South) district
Alignment drawn
none published: found by name
Documents
2
Verified facts
9 of 9
9 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

Bannigiri to Kanakapura Tq. Border via Gollahalli Chennammanapalya

OMMAS lists PMGSY-I work KN0202 as “Bannigiri to Kanakapura Tq. Border via Gollahalli Chennammanapalya”.

Road Name / Bridge Name: Bannigiri to Kanakapura Tq. Border via Gollahalli Chennammanapalya

[1]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 11

VerifiedOfficial record

Project / work ID

KN0202

OMMAS package number KN0202.

VerifiedOfficial record

Responsible agency

DPIU Of Ramanagaram

The programme implementation unit is recorded as “DPIU Of Ramanagaram”.

Programme Implementation Unit: DPIU Of Ramanagaram

[3]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 11

VerifiedOfficial record

Contractor

S K Putta Swamy

OMMAS lists the contractor for this work as “S K Putta Swamy”.

Contractor Name: S K Putta Swamy [27 Aug 2001]

[4]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 11

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹40.92 lakh

The sanction cost is recorded as 40.92 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

30-11-2002

The completion date column reads “Financial: 29-04-2006/ Physical: 30-11-2002”; the physical completion date is 30-11-2002.

Completion Date: Financial: 29-04-2006/ Physical: 30-11-2002

[9]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 11

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[10]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

6.000 km

Road length 6.000 km; 6.000 km recorded as completed.

VerifiedOfficial record

Stage of work

Completed

OMMAS records the stage of progress as “Completed”.

VerifiedOfficial record