B.M.Road to Bommanahalli

PMGSY-I · package KN0211 · Kanakpur block · Completed

Location
Kanakpur block, Ramanagara (Bengaluru South) district
Alignment drawn
none published: found by name
Documents
2
Verified facts
9 of 9
9 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

B.M.Road to Bommanahalli

OMMAS lists PMGSY-I work KN0211 as “B.M.Road to Bommanahalli”.

Road Name / Bridge Name: B.M.Road to Bommanahalli

[1]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4

VerifiedOfficial record

Project / work ID

KN0211

OMMAS package number KN0211.

VerifiedOfficial record

Responsible agency

DPIU Of Ramanagaram

The programme implementation unit is recorded as “DPIU Of Ramanagaram”.

Programme Implementation Unit: DPIU Of Ramanagaram

[3]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4

VerifiedOfficial record

Contractor

Karnataka Land Army Corporation

OMMAS lists the contractor for this work as “Karnataka Land Army Corporation”.

Contractor Name: Karnataka Land Army Corporation [07 Jul 2002]

[4]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹15.86 lakh

The sanction cost is recorded as 15.86 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

31-03-2004

The completion date column reads “Financial: 01-04-2005/ Physical: 31-03-2004”; the physical completion date is 31-03-2004.

Completion Date: Financial: 01-04-2005/ Physical: 31-03-2004

[9]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[10]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

1.450 km

Road length 1.450 km; 1.450 km recorded as completed.

VerifiedOfficial record

Stage of work

Completed

OMMAS records the stage of progress as “Completed”.

VerifiedOfficial record