Project record
B.M.Road to Bommanahalli
PMGSY-I · package KN0211 · Kanakpur block · Completed
- Location
- Kanakpur block, Ramanagara (Bengaluru South) district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 9 of 9
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
B.M.Road to Bommanahalli
OMMAS lists PMGSY-I work KN0211 as “B.M.Road to Bommanahalli”.
Road Name / Bridge Name: B.M.Road to Bommanahalli
[1]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Project / work ID
KN0211
OMMAS package number KN0211.
Package No.: KN0211
[2]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Responsible agency
DPIU Of Ramanagaram
The programme implementation unit is recorded as “DPIU Of Ramanagaram”.
Programme Implementation Unit: DPIU Of Ramanagaram
[3]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Contractor
Karnataka Land Army Corporation
OMMAS lists the contractor for this work as “Karnataka Land Army Corporation”.
Contractor Name: Karnataka Land Army Corporation [07 Jul 2002]
[4]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹15.86 lakh
The sanction cost is recorded as 15.86 (₹ lakh).
Sanction Cost: 15.86
[5]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-03-2004
The completion date column reads “Financial: 01-04-2005/ Physical: 31-03-2004”; the physical completion date is 31-03-2004.
Completion Date: Financial: 01-04-2005/ Physical: 31-03-2004
[9]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[10]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
1.450 km
Road length 1.450 km; 1.450 km recorded as completed.
Road Length (Kms): 1.450
[7]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4