Kanakapura-Sangam - Yadamaranahalli

PMGSY-I · package KN0219C · Kanakpur block · Completed

Location
Kanakpur block, Ramanagara (Bengaluru South) district
Alignment drawn
none published: found by name
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

Kanakapura-Sangam - Yadamaranahalli

OMMAS lists PMGSY-I work KN0219C as “Kanakapura-Sangam - Yadamaranahalli”.

Road Name / Bridge Name: Kanakapura-Sangam - Yadamaranahalli

[1]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 6

VerifiedOfficial record

Project / work ID

KN0219C

OMMAS package number KN0219C.

VerifiedOfficial record

Responsible agency

DPIU Of Ramanagaram

The programme implementation unit is recorded as “DPIU Of Ramanagaram”.

Programme Implementation Unit: DPIU Of Ramanagaram

[3]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 6

VerifiedOfficial record

Contractor

Sri Lakshman

OMMAS lists the contractor for this work as “Sri Lakshman”.

Contractor Name: Sri Lakshman [08 Dec 2006]

[4]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 6

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹41.30 lakh

The sanction cost is recorded as 41.30 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹2.65 lakh

The “5 Years Maintenance Cost Due” column shows 2.65 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

30-04-2008

The completion date column reads “Financial: 29-06-2009/ Physical: 30-04-2008”; the physical completion date is 30-04-2008.

Completion Date: Financial: 29-06-2009/ Physical: 30-04-2008

[10]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 6

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

2.640 km

Road length 2.640 km; 2.640 km recorded as completed.

VerifiedOfficial record

Stage of work

Completed

OMMAS records the stage of progress as “Completed”.

VerifiedOfficial record