T-11 in Nelamangala Taluk - T-04 at Solur

PMGSY-I · package KN0271 · Magadi block · Completed

Location
Magadi block, Ramanagara (Bengaluru South) district
Alignment drawn
none published: found by name
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

T-11 in Nelamangala Taluk - T-04 at Solur

OMMAS lists PMGSY-I work KN0271 as “T-11 in Nelamangala Taluk - T-04 at Solur”.

Road Name / Bridge Name: T-11 in Nelamangala Taluk - T-04 at Solur

[1]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 11

VerifiedOfficial record

Project / work ID

KN0271

OMMAS package number KN0271.

VerifiedOfficial record

Responsible agency

DPIU Of Ramanagaram

The programme implementation unit is recorded as “DPIU Of Ramanagaram”.

Programme Implementation Unit: DPIU Of Ramanagaram

[3]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 11

VerifiedOfficial record

Contractor

M G SHIVASHANKARA SWAMY

OMMAS lists the contractor for this work as “M G SHIVASHANKARA SWAMY”.

Contractor Name: M G SHIVASHANKARA SWAMY [28 Feb 2009]

[4]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 11

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹355.50 lakh

The sanction cost is recorded as 355.50 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹29.59 lakh

The “5 Years Maintenance Cost Due” column shows 29.59 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

30-09-2011

The completion date column reads “Financial: 03-03-2012/ Physical: 30-09-2011”; the physical completion date is 30-09-2011.

Completion Date: Financial: 03-03-2012/ Physical: 30-09-2011

[10]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 11

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

15.000 km

Road length 15.000 km; 15.000 km recorded as completed.

VerifiedOfficial record

Stage of work

Completed

OMMAS records the stage of progress as “Completed”.

VerifiedOfficial record