Project record
Marachanahalli - T01
PMGSY-I · package KN0280 · Channapatna block · Completed
- Location
- Channapatna block, Ramanagara (Bengaluru South) district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
Marachanahalli - T01
OMMAS lists PMGSY-I work KN0280 as “Marachanahalli - T01”.
Road Name / Bridge Name: Marachanahalli - T01
[1]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Project / work ID
KN0280
OMMAS package number KN0280.
Package No.: KN0280
[2]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Responsible agency
DPIU Of Ramanagaram
The programme implementation unit is recorded as “DPIU Of Ramanagaram”.
Programme Implementation Unit: DPIU Of Ramanagaram
[3]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Contractor
Ramanna H. Sharadalli
OMMAS lists the contractor for this work as “Ramanna H. Sharadalli”.
Contractor Name: Ramanna H. Sharadalli [11 Feb 2009]
[4]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹99.03 lakh
The sanction cost is recorded as 99.03 (₹ lakh).
Sanction Cost: 99.03
[5]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Maintenance cost due
₹8.30 lakh
The “5 Years Maintenance Cost Due” column shows 8.30 (₹ lakh).
5 Years Maintenance Cost Due: 8.30
[9]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
30-11-2009
The completion date column reads “Financial: 31-01-2011/ Physical: 30-11-2009”; the physical completion date is 30-11-2009.
Completion Date: Financial: 31-01-2011/ Physical: 30-11-2009
[10]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
4.180 km
Road length 4.180 km; 4.180 km recorded as completed.
Road Length (Kms): 4.180
[7]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-I (CSV export), p. 4