Project record

MRL8-Banthamma temple to MDR Tenginaikanahalli via Rachaiahnadoddi, Gurukeredoddi,Kothidimba

PMGSY-II · package KN28123 · Kanakpur block · Maintenance

Location
Kanakpur block, Ramanagara (Bengaluru South) district
Alignment drawn
none published: found by name
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

OMMAS lists PMGSY-II work KN28123 as “MRL8-Banthamma temple to MDR Tenginaikanahalli via Rachaiahnadoddi, Gurukeredoddi,Kothidimba”.

Road Name / Bridge Name: MRL8-Banthamma temple to MDR Tenginaikanahalli via Rachaiahnadoddi, Gurukeredoddi,Kothidimba

[1]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-II (CSV export), p. 1

VerifiedOfficial record

Project / work ID

KN28123

OMMAS package number KN28123.

VerifiedOfficial record

Responsible agency

DPIU Of Ramanagaram

The programme implementation unit is recorded as “DPIU Of Ramanagaram”.

Programme Implementation Unit: DPIU Of Ramanagaram

[3]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-II (CSV export), p. 1

VerifiedOfficial record

Contractor

Y V R CONSTRUCTIONS

OMMAS lists the contractor for this work as “Y V R CONSTRUCTIONS”.

Contractor Name: Y V R CONSTRUCTIONS [03 Mar 2014]

[4]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-II (CSV export), p. 1

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹156.13 lakh

The sanction cost is recorded as 156.13 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹15.15 lakh

The “5 Years Maintenance Cost Due” column shows 15.15 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

30-04-2016

The completion date column reads “Financial: 08-02-2017/ Physical: 30-04-2016”; the physical completion date is 30-04-2016.

Completion Date: Financial: 08-02-2017/ Physical: 30-04-2016

[10]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-II (CSV export), p. 1

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

5.180 km

Road length 5.180 km; 4.230 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record