Project record
MRL20-Thirumalegoudana Doddi To SH Via Jalamangla
PMGSY-III · package KN28140 · Ramanagar block · Maintenance
- Location
- Ramanagar block, Ramanagara (Bengaluru South) district
- Alignment drawn
- 914 m · official GIS
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
MRL20-Thirumalegoudana Doddi To SH Via Jalamangla
OMMAS lists PMGSY-III work KN28140 as “MRL20-Thirumalegoudana Doddi To SH Via Jalamangla”.
Road Name / Bridge Name: MRL20-Thirumalegoudana Doddi To SH Via Jalamangla
[1]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-III (CSV export), p. 4
Project / work ID
KN28140
OMMAS package number KN28140.
Package No.: KN28140
[2]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-III (CSV export), p. 4
Responsible agency
DPIU Of Ramanagaram
The programme implementation unit is recorded as “DPIU Of Ramanagaram”.
Programme Implementation Unit: DPIU Of Ramanagaram
[3]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-III (CSV export), p. 4
Contractor
M/s. KPJ CONSTRUCTION PVT LTD
OMMAS lists the contractor for this work as “M/s. KPJ CONSTRUCTION PVT LTD”.
Contractor Name: M/s. KPJ CONSTRUCTION PVT LTD [28 Jul 2021]
[4]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-III (CSV export), p. 4
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹190.86 lakh
The sanction cost is recorded as 190.86 (₹ lakh).
Sanction Cost: 190.86
[5]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-III (CSV export), p. 4
Maintenance cost due
₹21.10 lakh
The “5 Years Maintenance Cost Due” column shows 21.10 (₹ lakh).
5 Years Maintenance Cost Due: 21.10
[9]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-III (CSV export), p. 4
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
30-12-2023
The completion date column reads “Financial: 16-12-2024/ Physical: 30-12-2023”; the physical completion date is 30-12-2023.
Completion Date: Financial: 16-12-2024/ Physical: 30-12-2023
[10]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-III (CSV export), p. 4
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
3.930 km
Road length 3.930 km; 3.930 km recorded as completed.
Road Length (Kms): 3.930
[7]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-III (CSV export), p. 4
Stage of work
Maintenance
OMMAS records the stage of progress as “Maintenance”.
Stage of Progress: Maintenance
[8]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-III (CSV export), p. 4