Project record

MRL14-Seegekuppe To Chakrabhavi Via Hagalakuppe, Honnaiahanapalya

PMGSY-III · package KN28147 · Magadi block · Maintenance

Location
Magadi block, Ramanagara (Bengaluru South) district
Alignment drawn
3.8 km · official GIS
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

MRL14-Seegekuppe To Chakrabhavi Via Hagalakuppe, Honnaiahanapalya

OMMAS lists PMGSY-III work KN28147 as “MRL14-Seegekuppe To Chakrabhavi Via Hagalakuppe, Honnaiahanapalya”.

Road Name / Bridge Name: MRL14-Seegekuppe To Chakrabhavi Via Hagalakuppe, Honnaiahanapalya

[1]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-III (CSV export), p. 3

VerifiedOfficial record

Project / work ID

KN28147

OMMAS package number KN28147.

VerifiedOfficial record

Responsible agency

DPIU Of Ramanagaram

The programme implementation unit is recorded as “DPIU Of Ramanagaram”.

Programme Implementation Unit: DPIU Of Ramanagaram

[3]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-III (CSV export), p. 3

VerifiedOfficial record

Contractor

M/s. KPJ CONSTRUCTION PVT LTD

OMMAS lists the contractor for this work as “M/s. KPJ CONSTRUCTION PVT LTD”.

Contractor Name: M/s. KPJ CONSTRUCTION PVT LTD [28 Jul 2021]

[4]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-III (CSV export), p. 3

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹324.58 lakh

The sanction cost is recorded as 324.58 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹28.37 lakh

The “5 Years Maintenance Cost Due” column shows 28.37 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

03-01-2024

The completion date column reads “Financial: 16-12-2024/ Physical: 03-01-2024”; the physical completion date is 03-01-2024.

Completion Date: Financial: 16-12-2024/ Physical: 03-01-2024

[10]SLR: Statewise List of Works — Karnataka, Ramanagara, PMGSY-III (CSV export), p. 3

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

5.200 km

Road length 5.200 km; 5.720 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record