Project record
Pattanayakanahalli Dwarakunte Doddahulikunte
PMGSY-I · package KN2503 · Sira block · Completed
- Location
- Sira block, Tumakuru district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 9 of 9
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
Pattanayakanahalli Dwarakunte Doddahulikunte
OMMAS lists PMGSY-I work KN2503 as “Pattanayakanahalli Dwarakunte Doddahulikunte”.
Road Name / Bridge Name: Pattanayakanahalli Dwarakunte Doddahulikunte
[1]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 18
Project / work ID
KN2503
OMMAS package number KN2503.
Package No.: KN2503
[2]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 18
Responsible agency
DPIU Of Tumkur
The programme implementation unit is recorded as “DPIU Of Tumkur”.
Programme Implementation Unit: DPIU Of Tumkur
[3]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 18
Contractor
N Ramachandra Reddy
OMMAS lists the contractor for this work as “N Ramachandra Reddy”.
Contractor Name: N Ramachandra Reddy [29 Aug 2001]
[4]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 18
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹62.47 lakh
The sanction cost is recorded as 62.47 (₹ lakh).
Sanction Cost: 62.47
[5]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 18
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-07-2002
The completion date column reads “Financial: 01-04-2005/ Physical: 31-07-2002”; the physical completion date is 31-07-2002.
Completion Date: Financial: 01-04-2005/ Physical: 31-07-2002
[9]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 18
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[10]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
10.300 km
Road length 10.300 km; 10.300 km recorded as completed.
Road Length (Kms): 10.300
[7]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 18
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 18