MRL3-Road from MDR-4 K-Bydarahalli to MDR-3 via R-Byadarahalli, kempanahalli, and Tavarakere.
PMGSY-II · package KN25104 · Kunigal block · Maintenance
- Location
- Kunigal block, Tumakuru district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
OMMAS lists PMGSY-II work KN25104 as “MRL3-Road from MDR-4 K-Bydarahalli to MDR-3 via R-Byadarahalli, kempanahalli, and Tavarakere.”.
Road Name / Bridge Name: MRL3-Road from MDR-4 K-Bydarahalli to MDR-3 via R-Byadarahalli, kempanahalli, and Tavarakere.
[1]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-II (CSV export), p. 1
Project / work ID
KN25104
OMMAS package number KN25104.
Package No.: KN25104
[2]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-II (CSV export), p. 1
Responsible agency
DPIU Of Tumkur
The programme implementation unit is recorded as “DPIU Of Tumkur”.
Programme Implementation Unit: DPIU Of Tumkur
[3]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-II (CSV export), p. 1
Contractor
OMMAS lists the contractor for this work as “M/S K Gowda and Company [04 Mar 2014], Ajay Shree Electricals [17 Aug 2015], Ajay Shree Electricals”.
Contractor Name: M/S K Gowda and Company [04 Mar 2014], Ajay Shree Electricals [17 Aug 2015], Ajay Shree Electricals [17 Aug 2015]
[4]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-II (CSV export), p. 1
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹530.69 lakh
The sanction cost is recorded as 530.69 (₹ lakh).
Sanction Cost: 530.69
[5]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-II (CSV export), p. 1
Maintenance cost due
₹33.84 lakh
The “5 Years Maintenance Cost Due” column shows 33.84 (₹ lakh).
5 Years Maintenance Cost Due: 33.84
[9]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-II (CSV export), p. 1
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
30-09-2015
The completion date column reads “Financial: 23-03-2017/ Physical: 30-09-2015”; the physical completion date is 30-09-2015.
Completion Date: Financial: 23-03-2017/ Physical: 30-09-2015
[10]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-II (CSV export), p. 1
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
11.570 km
Road length 11.570 km; 11.450 km recorded as completed.
Road Length (Kms): 11.570
[7]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-II (CSV export), p. 1
Stage of work
Maintenance
OMMAS records the stage of progress as “Maintenance”.
Stage of Progress: Maintenance