CONSTRUCTION OF BOX TYPE BRIDGE AT CH 60M OF ROAD JOINING HAMPLAPURA MDR TO TALUK BORDER VIA SAMPIGE
PMGSY-III · package KN25123A · Turuvekere block · Completed
- Location
- Turuvekere block, Tumakuru district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 8 of 8
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
OMMAS lists PMGSY-III work KN25123A as “CONSTRUCTION OF BOX TYPE BRIDGE AT CH 60M OF ROAD JOINING HAMPLAPURA MDR TO TALUK BORDER VIA SAMPIGE”.
Road Name / Bridge Name: CONSTRUCTION OF BOX TYPE BRIDGE AT CH 60M OF ROAD JOINING HAMPLAPURA MDR TO TALUK BORDER VIA SAMPIGE
[1]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 10
Project / work ID
KN25123A
OMMAS package number KN25123A.
Package No.: KN25123A
[2]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 10
Responsible agency
DPIU Of Tumkur
The programme implementation unit is recorded as “DPIU Of Tumkur”.
Programme Implementation Unit: DPIU Of Tumkur
[3]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 10
Contractor
M/s Dodde Gowda Construction.Pvt.Ltd
OMMAS lists the contractor for this work as “M/s Dodde Gowda Construction.Pvt.Ltd”.
Contractor Name: M/s Dodde Gowda Construction.Pvt.Ltd [01 Dec 2020]
[4]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 10
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹33.59 lakh
The sanction cost is recorded as 33.59 (₹ lakh).
Sanction Cost: 33.59
[5]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 10
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
01-05-2022
The completion date column reads “Financial: 20-10-2022/ Physical: 01-05-2022”; the physical completion date is 01-05-2022.
Completion Date: Financial: 20-10-2022/ Physical: 01-05-2022
[8]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 10
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[9]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[7]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 10