Project record

MRL02-Huliyar-Anekatte Road to NH234 Via Thimmalapura, Hosahalli palya and Hosahalli

PMGSY-III · package KN25126 · C.N.Halli block · Maintenance

Location
C.N.Halli block, Tumakuru district
Alignment drawn
4.9 km · official GIS
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

MRL02-Huliyar-Anekatte Road to NH234 Via Thimmalapura, Hosahalli palya and Hosahalli

OMMAS lists PMGSY-III work KN25126 as “MRL02-Huliyar-Anekatte Road to NH234 Via Thimmalapura, Hosahalli palya and Hosahalli”.

Road Name / Bridge Name: MRL02-Huliyar-Anekatte Road to NH234 Via Thimmalapura, Hosahalli palya and Hosahalli

[1]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Project / work ID

KN25126

OMMAS package number KN25126.

VerifiedOfficial record

Responsible agency

DPIU Of Tumkur

The programme implementation unit is recorded as “DPIU Of Tumkur”.

Programme Implementation Unit: DPIU Of Tumkur

[3]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Contractor

C.R.Harish [19 Jun 2020], C.R.Harish

OMMAS lists the contractor for this work as “C.R.Harish [19 Jun 2020], C.R.Harish”.

Contractor Name: C.R.Harish [19 Jun 2020], C.R.Harish [19 Jun 2020]

[4]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹538.35 lakh

The sanction cost is recorded as 538.35 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹40.54 lakh

The “5 Years Maintenance Cost Due” column shows 40.54 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

20-09-2023

The completion date column reads “Financial: 27-03-2025/ Physical: 20-09-2023”; the physical completion date is 20-09-2023.

Completion Date: Financial: 27-03-2025/ Physical: 20-09-2023

[10]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

6.880 km

Road length 6.880 km; 6.580 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record