Project record

MRL09-Kuppur to Ankasandra via Machasandra, Abbujihalli, Bevihalli Gate, Bevinahalli

PMGSY-III · package KN25127 · C.N.Halli block · Maintenance

Location
C.N.Halli block, Tumakuru district
Alignment drawn
12 m · official GIS
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

MRL09-Kuppur to Ankasandra via Machasandra, Abbujihalli, Bevihalli Gate, Bevinahalli

OMMAS lists PMGSY-III work KN25127 as “MRL09-Kuppur to Ankasandra via Machasandra, Abbujihalli, Bevihalli Gate, Bevinahalli”.

Road Name / Bridge Name: MRL09-Kuppur to Ankasandra via Machasandra, Abbujihalli, Bevihalli Gate, Bevinahalli

[1]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Project / work ID

KN25127

OMMAS package number KN25127.

VerifiedOfficial record

Responsible agency

DPIU Of Tumkur

The programme implementation unit is recorded as “DPIU Of Tumkur”.

Programme Implementation Unit: DPIU Of Tumkur

[3]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Contractor

M/s. Apoorva Construction Co.,

OMMAS lists the contractor for this work as “M/s. Apoorva Construction Co.,”.

Contractor Name: M/s. Apoorva Construction Co., [15 Jan 2021]

[4]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹405.64 lakh

The sanction cost is recorded as 405.64 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹36.00 lakh

The “5 Years Maintenance Cost Due” column shows 36.00 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

20-02-2023

The completion date column reads “Financial: 30-03-2024/ Physical: 20-02-2023”; the physical completion date is 20-02-2023.

Completion Date: Financial: 30-03-2024/ Physical: 20-02-2023

[10]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 1

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

6.110 km

Road length 6.110 km; 6.110 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record