Project record

MRL10-Yeliyur to NH-48 via Alkere and Kallanayakanahalli

PMGSY-III · package KN25135 · Kunigal block · Maintenance

Location
Kunigal block, Tumakuru district
Alignment drawn
3.9 km · official GIS
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

MRL10-Yeliyur to NH-48 via Alkere and Kallanayakanahalli

OMMAS lists PMGSY-III work KN25135 as “MRL10-Yeliyur to NH-48 via Alkere and Kallanayakanahalli”.

Road Name / Bridge Name: MRL10-Yeliyur to NH-48 via Alkere and Kallanayakanahalli

[1]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 4

VerifiedOfficial record

Project / work ID

KN25135

OMMAS package number KN25135.

VerifiedOfficial record

Responsible agency

DPIU Of Tumkur

The programme implementation unit is recorded as “DPIU Of Tumkur”.

Programme Implementation Unit: DPIU Of Tumkur

[3]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 4

VerifiedOfficial record

Contractor

M/S K Gowda and Company [31 Jul 2020], M/S K Gowda and Company

OMMAS lists the contractor for this work as “M/S K Gowda and Company [31 Jul 2020], M/S K Gowda and Company”.

Contractor Name: M/S K Gowda and Company [31 Jul 2020], M/S K Gowda and Company [31 Jul 2020]

[4]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 4

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹236.81 lakh

The sanction cost is recorded as 236.81 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹22.98 lakh

The “5 Years Maintenance Cost Due” column shows 22.98 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

25-07-2022

The completion date column reads “Financial: -/ Physical: 25-07-2022”; the physical completion date is 25-07-2022.

Completion Date: Financial: -/ Physical: 25-07-2022

[10]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 4

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

3.900 km

Road length 3.900 km; 3.900 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record