Project record
Dandinadibba Hanumanahalli to Gondanapalya
PMGSY-I · package KN2515 · Madhugiri block · Completed
- Location
- Madhugiri block, Tumakuru district
- Alignment drawn
- none published: found by name
- Documents
- 2
- Verified facts
- 10 of 10
Who is responsible
The project, the agency that executes it, and the contractor named in the records.
Project
Dandinadibba Hanumanahalli to Gondanapalya
OMMAS lists PMGSY-I work KN2515 as “Dandinadibba Hanumanahalli to Gondanapalya”.
Road Name / Bridge Name: Dandinadibba Hanumanahalli to Gondanapalya
[1]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 14
Project / work ID
KN2515
OMMAS package number KN2515.
Package No.: KN2515
[2]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 14
Responsible agency
DPIU Of Tumkur
The programme implementation unit is recorded as “DPIU Of Tumkur”.
Programme Implementation Unit: DPIU Of Tumkur
[3]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 14
Contractor
Shivananda
OMMAS lists the contractor for this work as “Shivananda”.
Contractor Name: Shivananda [13 Sep 2004]
[4]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 14
Money
Amounts as stated in the records, with their units.
Sanctioned cost
₹38.50 lakh
The sanction cost is recorded as 38.50 (₹ lakh).
Sanction Cost: 38.50
[5]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 14
Maintenance cost due
₹2.70 lakh
The “5 Years Maintenance Cost Due” column shows 2.70 (₹ lakh).
5 Years Maintenance Cost Due: 2.70
[9]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 14
Dates and obligations
When the work was awarded and completed, and how long the contractor must maintain it.
Completion date
31-12-2005
The completion date column reads “Financial: 31-03-2007/ Physical: 31-12-2005”; the physical completion date is 31-12-2005.
Completion Date: Financial: 31-03-2007/ Physical: 31-12-2005
[10]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 14
Defect liability / maintenance period
5 years
The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.
…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…
[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40
Scope and condition
What the work was meant to include, and what inspections and audits recorded.
Planned scope
1.720 km
Road length 1.720 km; 1.720 km recorded as completed.
Road Length (Kms): 1.720
[7]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 14
Stage of work
Completed
OMMAS records the stage of progress as “Completed”.
Stage of Progress: Completed
[8]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-I (CSV export), p. 14