Project record

T16-Y.N Hosakote-Bestrahalli Road to A.P Border via Siddapura,Jalodu, chikkajalodu

PMGSY-III · package KN25155 · Pavagada block · Maintenance

Location
Pavagada block, Tumakuru district
Alignment drawn
3.4 km · official GIS
Documents
2
Verified facts
10 of 10
10 verified in official records0 open questions

Who is responsible

The project, the agency that executes it, and the contractor named in the records.

Project

T16-Y.N Hosakote-Bestrahalli Road to A.P Border via Siddapura,Jalodu, chikkajalodu

OMMAS lists PMGSY-III work KN25155 as “T16-Y.N Hosakote-Bestrahalli Road to A.P Border via Siddapura,Jalodu, chikkajalodu”.

Road Name / Bridge Name: T16-Y.N Hosakote-Bestrahalli Road to A.P Border via Siddapura,Jalodu, chikkajalodu

[1]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 6

VerifiedOfficial record

Project / work ID

KN25155

OMMAS package number KN25155.

VerifiedOfficial record

Responsible agency

DPIU Of Tumkur

The programme implementation unit is recorded as “DPIU Of Tumkur”.

Programme Implementation Unit: DPIU Of Tumkur

[3]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 6

VerifiedOfficial record

Contractor

H.NARAYANAPPA [21 Aug 2020], H.NARAYANAPPA

OMMAS lists the contractor for this work as “H.NARAYANAPPA [21 Aug 2020], H.NARAYANAPPA”.

Contractor Name: H.NARAYANAPPA [21 Aug 2020], H.NARAYANAPPA [21 Aug 2020]

[4]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 6

VerifiedOfficial record

Money

Amounts as stated in the records, with their units.

Sanctioned cost

₹362.34 lakh

The sanction cost is recorded as 362.34 (₹ lakh).

VerifiedOfficial record

Maintenance cost due

₹37.09 lakh

The “5 Years Maintenance Cost Due” column shows 37.09 (₹ lakh).

VerifiedOfficial record

Dates and obligations

When the work was awarded and completed, and how long the contractor must maintain it.

Completion date

26-07-2022

The completion date column reads “Financial: 24-05-2024/ Physical: 26-07-2022”; the physical completion date is 26-07-2022.

Completion Date: Financial: 24-05-2024/ Physical: 26-07-2022

[10]SLR: Statewise List of Works — Karnataka, Tumakuru, PMGSY-III (CSV export), p. 6

VerifiedOfficial record

Defect liability / maintenance period

5 years

The PMGSY Programme Guidelines (para 17.2) state that all PMGSY roads are covered by 5-year maintenance contracts entered into with the same contractor as the construction contract.

…PMGSY roads (including associated Main Rural Links / Through Routes of PMGSY link routes) will be covered by 5-year maintenance contracts, (see Para 8.6) to be entered into along with the construction contract, with the…

[11]Pradhan Mantri Gram Sadak Yojana — Programme Guidelines, p. 40

VerifiedOfficial record

Scope and condition

What the work was meant to include, and what inspections and audits recorded.

Planned scope

7.100 km

Road length 7.100 km; 7.100 km recorded as completed.

VerifiedOfficial record

Stage of work

Maintenance

OMMAS records the stage of progress as “Maintenance”.

VerifiedOfficial record